781
Comment:
|
1044
|
Deletions are marked like this. | Additions are marked like this. |
Line 6: | Line 6: |
* Fabian, Mark and Liu-kun did BS installation at Kamioka: * Debugged the issue with the BF keystone being tilted enough to cause rubbing on the yoke for the magnets. It was solved by moving the yoke ≈1 mm taking advantage of the oversized holes. * Measured the height of the payload as a function of trim mass. The BF spring seems to have a slightly lower load capacity and a rather higher spring constant than when it was remeasured by Hirata-san. * Removed IM trim mass to set the average height of the keystone to the CAD value. * Moved IM trim mass around to set the pitch of the dummy BS. * Hirata-san * TBD. |
* Mark and Hirata-san at Mitaka * Gathered parts for cable making. * Mark and Hirata-san at Kamioka: * Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame. * Installed two more LPCDs and the stepper motor driver in the PR2 rack. * Ran cables from the rack to the second and third sat amps (for the IRM OSEMs). * Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs. * Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement. * Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4). * Added extension to the IM pico cable for the BF yaw pico. * Made LVDT adapter cable. * Mark worked on schedule. |
Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
- Type B Past Week Summary
- Mark and Hirata-san at Mitaka
- Gathered parts for cable making.
- Mark and Hirata-san at Kamioka:
- Replaced the floor panels that had been taken from the PR2 area (filling in the hole in the floor) and found/installed two new panels to act as bridges near the BS assembly frame.
- Installed two more LPCDs and the stepper motor driver in the PR2 rack.
- Ran cables from the rack to the second and third sat amps (for the IRM OSEMs).
- Added a second DIO card in the rack and connected it to the BIO inputs and outputs of the new LPCDs.
- Started making extension cables for RM-H2 and -H3 OSEMs but gave up due to complicated grounding arrangement.
- Washed four 40-cm D-Sub-9 ribbon cables to use as temporary extensions (maybe also for H1/H4).
- Added extension to the IM pico cable for the BF yaw pico.
- Made LVDT adapter cable.
- Mark worked on schedule.
- Mark and Hirata-san at Mitaka