Scraps of text for incorporation in the VIS Meeting Minutes
KAGRA/Subgroups/VIS/MeetingNAOJ
Type B (Mark)
Past two weeks report
At Kamioka (Mark, Enzo, Kozu-kun):
- Supported IA team.
- Replaced LPCDs for IM OSEMs with HPCDs for increased pitch/yaw range.
- Re-zeroed OL after significant change of beam position during IA.
- Re-laid-out OL to improve focus of lens to LEN QPD.
- Offloaded the pitch/yaw actuation at the IM OSEMs using the IM pitch/yaw picos.
- Enzo worked on design of control loops using the OL.
- Kozu-kun worked on diagonalizing the OL.
Mitaka (Fabian, Hirata-san):
- Hirata-san published his inventory of SR parts on Dropbox.
Plan for week of 11/13
Kamioka: Mark
- Attend commissioning workshop at U Toyama.
- Be person-on-site for BF work.
- Set up for mirror gluing.
Mitaka: Fabian and Hirata-san
- SR procurement.
- New PI GAS FR design.
- BS LBB ballast mass design.
- SR cable lamp design.
Mitaka: Enzo and Kozu-kun (Wed, Thu)
- Servos
- TFs of BF
- Documentation