Differences between revisions 10 and 11
Revision 10 as of 2016-12-01 11:20:36
Size: 2711
Editor: NaokoOhishi
Comment:
Revision 11 as of 2016-12-01 11:22:44
Size: 2798
Editor: NaokoOhishi
Comment:
Deletions are marked like this. Additions are marked like this.
Line 35: Line 35:
  * Inside the IFI chamber, it is crowded because large IFI is already set.   * Inside the IFI chamber, there already is set large IFI;
    it is so crowded and seems to be difficult installing IMMT suspension from the side flange.
Line 37: Line 38:
  * Need discussion with Hirose-san about clean control.   * Need discussion with Hirose-san about cleanliness control.

Agenda/Minutes of the VIS Meeting on 2016/12/2

2016/12/2 13:30 -

Participants:

Progress report

Schedule Chart (PDF,MPP)

Type-A (Takahashi)

  • Minutes of Type-A Meeting

  • Installation: The first transportation to Y-end for Type-A items is scheduled on 7-9th. The second one is scheduled in early January.
  • Pre-isolator: Cable connection and check were finished. Two sets have been shipped on 1st.
  • EQ stop, release sensor, dummy payload: The parts remained will be delivered on 12th.
  • BF damper: The production is on going.
  • Maraging wire: Ordered. The first set will be delivered by 20th January.
  • Tooling for installation: The hoist tool was ordered.

Type B (Mark)

  • Put a report here

Type-Bp (Shoda)

  • Put a report here

IMMT (Ohishi)

  • Drawings
    • Materials already ordered will be delivered on 28th Dec.
  • Remaining parts status
    • PZT holder
  • Magnet and standoff fixture jig
    • Still in Kashiwa (perhaps.. I asked Hirose-san to return it but he didn't reply to me.)
    • Need at least two new parts and two sims for different thickness of the mirror.
  • Hanging and Installation Procedure:
    • Inside the IFI chamber, there already is set large IFI;
      • it is so crowded and seems to be difficult installing IMMT suspension from the side flange.
    • We are planning to install IMMT2 from the top flange.
    • Need discussion with Hirose-san about cleanliness control.
    • IMMTs are not on the center line where cranes move.
      • So perhaps we need to move IMMT by hand after we install it from the top flange.
  • Cables:
  • Digital models
  • Mirror
  • Others
    • Japan Tungsten will send a sample of wires.

Watchdog system (Tanaka)

  • Put a report here

Safety

  • Incidents:
  • Foreseen risks:

Discussion

  • Mirror box modification

Site work plan for the next week

  • Mon: BS
  • Tue: BS
  • Wed: BS/Type-A transportation
  • Thu: BS/Type-A transportation
  • Fri: BS/Type-A transportation

Travel Plans

  • Travel (Week of 12/5):
    • Takahashi: 12/6-12/9
    • Shoda:
    • Mark: 12/5-12/9
    • Fabian: 12/5-12/9
    • Okutomi:
    • Fujii:
    • Ishizaki: 12/6-12/9
    • Hirata:
    • Sato:
    • Enzo: 12/5-12/9
    • Ohishi:
  • Travel (Week of 12/12):
    • Takahashi:
    • Shoda:
    • Mark:
    • Fabian:
    • Okutomi:
    • Fujii:
    • Ishizaki:
    • Hirata:
    • Sato:
    • Enzo:
    • Ohishi:

Next meeting

On 2016/12/9(Fri)

KAGRA/Subgroups/VIS/VISMinutes20161202 (last edited 2016-12-02 18:47:27 by YoichiAso)