1659
Comment:
|
2967
|
Deletions are marked like this. | Additions are marked like this. |
Line 8: | Line 8: |
Schedule Chart : ([[https://www.dropbox.com/s/035etsa8bbfzth2/VIS%20Overall%20Schedule-20170620.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/v9cqbycq6vgggng/VIS%20Overall%20Schedule-20170620.mpp?dl=0|MPP]]) | Schedule Chart : ([[https://www.dropbox.com/s/rbwjf67jwdq0c98/VIS%20Overall%20Schedule-20170707.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/1s44hs3eyh3n7s3/VIS%20Overall%20Schedule-20170707.mpp?dl=0|MPP]]) |
Line 16: | Line 16: |
[X-end] * Installed the hand lifter and pallets. [Y-end] 3rd(Mon) * Checked the ACCs with the driver. 4th(Tue) * No site work. 5th(Wed) * Adjusted the height of keystone in the TF. The FR was set at the lowest position. * Adjusted the height of SF damper. * Adjusted the yaw of wire receptacle in the TF. * Attached the secondary coils for BF damper. 6th(Thr) * Set the LVDT drives for the BF damper. * Closed the feedtrough flanges. * Removed the spacers under the F3. * Checked cable connection for the ACCs. * Closed the chamber. 7th(Fri) * Checked whether the 2.4m wire could be installed from the cryostat. * Adjusted the position of BF damper. Weekend * Measure the transfer functions. |
|
Line 17: | Line 43: |
* Remove the DP. * Test the connection with the cryo-payload. * Start the pre-assembly of BF damper in X-end. |
|
Line 32: | Line 61: |
*Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).--> *Ongoing --> *Order electronic parts -->Done. *Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress). |
|
Line 33: | Line 67: |
*Start production of equipment(As soon as parts are delivered). *Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing. |
Agenda/Minutes of the VIS Meeting on 2017/7/7
2017/7/7 13:30 -
Participants:
Progress report
- Type-A:
- Type-B:
- Type-Bp:
Type-A (Takahashi)
Past week report
[X-end]
- Installed the hand lifter and pallets.
[Y-end] 3rd(Mon)
- Checked the ACCs with the driver.
4th(Tue)
- No site work.
5th(Wed)
- Adjusted the height of keystone in the TF. The FR was set at the lowest position.
- Adjusted the height of SF damper.
- Adjusted the yaw of wire receptacle in the TF.
- Attached the secondary coils for BF damper.
6th(Thr)
- Set the LVDT drives for the BF damper.
- Closed the feedtrough flanges.
- Removed the spacers under the F3.
- Checked cable connection for the ACCs.
- Closed the chamber.
7th(Fri)
- Checked whether the 2.4m wire could be installed from the cryostat.
- Adjusted the position of BF damper.
Weekend
- Measure the transfer functions.
Plan for coming weeks
- Remove the DP.
- Test the connection with the cryo-payload.
- Start the pre-assembly of BF damper in X-end.
Type B (Mark)
Past week report
Plan for coming weeks
Type-Bp (Shoda)
Past week report
Plan for coming weeks
IMMT (Ohishi)
Past week report
Plan for coming weeks
Watchdog system (Tanaka)
Past week report
Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
Ongoing -->
Order electronic parts -->Done.
Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress).
Plan for coming weeks
- Start production of equipment(As soon as parts are delivered).
Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing.
Other site works
- 7/10-?: Lighting installation in the MCE and SR clean booths
Safety
- Incidents:
- Foreseen risks
- Type-A:
- Type-B:
- Type-Bp:
Discussion
Travel Plans
- Travel (Week of 7/10):
- Takahashi: 10 - 14
- Okutomi: 10 - 14
- Sato: 10 - 14
- Ishizaki: 10 - 13
- Mark: 10 - 14
- Fabian: 10 - 14
- Hirata: 10 - 14
- Enzo: 10 - 14
- Shoda: 10 - 14
- Ohishi:
- Fujii:
- Tanaka:
- Komori (Ando lab.): 10 - 14
- Hashimoto(Hosei): 10 - 13
- Travel (Week of 7/17):
- Takahashi:
- Okutomi:
- Sato:
- Ishizaki:
- Mark:
- Fabian:
- Hirata:
- Enzo:
- Shoda:
- Ohishi:
- Fujii:
- Tanaka:
- Komori (Ando lab.):
- Hashimoto(Hosei):
Next meeting
On 2017/7/14(Fri) Next F2F: 7/??