Line 8: Line 8:
Schedule Chart : ([[https://www.dropbox.com/s/035etsa8bbfzth2/VIS%20Overall%20Schedule-20170620.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/v9cqbycq6vgggng/VIS%20Overall%20Schedule-20170620.mpp?dl=0|MPP]]) Schedule Chart : ([[https://www.dropbox.com/s/rbwjf67jwdq0c98/VIS%20Overall%20Schedule-20170707.pdf?dl=0|PDF]],[[https://www.dropbox.com/s/1s44hs3eyh3n7s3/VIS%20Overall%20Schedule-20170707.mpp?dl=0|MPP]])
Line 16: Line 16:

[X-end]
 * Installed the hand lifter and pallets.

[Y-end]

3rd(Mon)
  * Checked the ACCs with the driver.
4th(Tue)
  * No site work.
5th(Wed)
  * Adjusted the height of keystone in the TF. The FR was set at the lowest position.
  * Adjusted the height of SF damper.
  * Adjusted the yaw of wire receptacle in the TF.
  * Attached the secondary coils for BF damper.
6th(Thr)
  * Set the LVDT drives for the BF damper.
  * Closed the feedtrough flanges.
  * Removed the spacers under the F3.
  * Checked cable connection for the ACCs.
  * Closed the chamber.
7th(Fri)
  * Checked whether the 2.4m wire could be installed from the cryostat.
  * Adjusted the position of BF damper.
Weekend
  * Measure the transfer functions.
Line 17: Line 44:
 * Remove the DP.
 * Test the connection with the cryo-payload.
 * Start the pre-assembly of BF damper in X-end.
Line 28: Line 58:
 * Assembled magnet fixture jig at Kamioka.
Line 29: Line 60:
 * Gluing magnets on IMMT mirrors at Kamioka in the presence of Takahashi-san.
Line 32: Line 64:
   *Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->
        *Ongoing -->
             *Order electronic parts -->Done.
             *Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress).
Line 33: Line 70:
   *Start production of equipment(As soon as parts are delivered).
   *Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing.

Agenda/Minutes of the VIS Meeting on 2017/7/7

2017/7/7 13:30 -

Participants:

Progress report

Schedule Chart : (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

[X-end]

  • Installed the hand lifter and pallets.

[Y-end]

3rd(Mon)

  • Checked the ACCs with the driver.

4th(Tue)

  • No site work.

5th(Wed)

  • Adjusted the height of keystone in the TF. The FR was set at the lowest position.
  • Adjusted the height of SF damper.
  • Adjusted the yaw of wire receptacle in the TF.
  • Attached the secondary coils for BF damper.

6th(Thr)

  • Set the LVDT drives for the BF damper.
  • Closed the feedtrough flanges.
  • Removed the spacers under the F3.
  • Checked cable connection for the ACCs.
  • Closed the chamber.

7th(Fri)

  • Checked whether the 2.4m wire could be installed from the cryostat.
  • Adjusted the position of BF damper.

Weekend

  • Measure the transfer functions.

Plan for coming weeks

  • Remove the DP.
  • Test the connection with the cryo-payload.
  • Start the pre-assembly of BF damper in X-end.

Type B (Mark)

Past week report

Plan for coming weeks

Type-Bp (Shoda)

Past week report

Plan for coming weeks

IMMT (Ohishi)

Past week report

  • Assembled magnet fixture jig at Kamioka.

Plan for coming weeks

  • Gluing magnets on IMMT mirrors at Kamioka in the presence of Takahashi-san.

Watchdog system (Tanaka)

Past week report

  • Creation of extended I/O PCB(plot type (With the Main 4ch WDS box and I/O box,I/O board For relay).-->

    • Ongoing -->

      • Order electronic parts -->Done.

      • Order PCB's(Ex-I/O Interface and relative PCB's) -->Ordering(PCB data of vendor is in progress).

Plan for coming weeks

  • Start production of equipment(As soon as parts are delivered).
  • Adjustment of experiment schedule etc. in the KAGRA side start. --> Ongoing.

Other site works

  • 7/10-?: Lighting installation in the MCE and SR clean booths

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

Travel Plans

  • Travel (Week of 7/10):
    • Takahashi: 10 - 14
    • Okutomi: 10 - 14
    • Sato: 10 - 14
    • Ishizaki: 10 - 13
    • Mark: 10 - 14
    • Fabian: 10 - 14
    • Hirata: 10 - 14
    • Enzo: 10 - 14
    • Shoda: 10 - 14
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Komori (Ando lab.): 10 - 14
    • Hashimoto(Hosei): 10 - 13
  • Travel (Week of 7/17):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Komori (Ando lab.):
    • Hashimoto(Hosei):

Next meeting

On 2017/7/14(Fri) Next F2F: 7/??