Line 33: Line 33:
 * Hirata-san worked on procurement of magnets, payload parts, and also got the delivery of the ferromagnetic disks expedited so we could have them this week.
Line 34: Line 35:
==== Plan for week of 12/11 ==== Plan for week of 12/11 ====

Agenda/Minutes of the VIS Meeting on 2017/12/8

2017/12/8 13:30 -

Participants:

Progress report

Schedule Chart

Type-A : (PDF,MPP)

Type-B: (PDF,MPP)

  • Type-A:
  • Type-B:
  • Type-Bp:

Type-A (Takahashi)

Past week report

Plan for coming weeks

Type B (Mark)

Past week report

  • Mark analyzed the QPD data from Friday 12/1 and derived matrices to diagonalize the QPD, and calibrate output in µrad. In the process an error in the IM OSEM diagonalization was discovered: the P and Y gains were low by a factor 2.
  • Mark re-zeroed the QPD after noting the micrometer readings so we can do TFs over the weekend.
  • We prepared for the SR2 gluing:
    • We aligned the SR2 in the box with the wedge on the correct side.
    • We checked that the remachined BS prism holders fit on the PR2 mirror box.
    • We checked that with Tatsumi-san's support ring, the prisms would go on at the right height.
    • We checked the new magnet jigs.
  • We glued ferromagnetic disks in a large number of IM flag tips and flag bases, and in the SR magnet jigs.
  • We also glued SR magnets in the magnet bases.
  • Hirata-san worked on procurement of magnets, payload parts, and also got the delivery of the ferromagnetic disks expedited so we could have them this week.

Plan for week of 12/11

  • Mark, Fabian, Enzo, Kozu-kun (Mon-Thu only), Hirata-san, Shoda-san at Kamioka.
  • Mirror gluing.
  • IM assembly and pico test.
  • Assembly frame alignment and optical table centering.
  • Move trolley system from SR3.
  • OL setup.

Plan for week of 12/18

  • Shoda-san vacation
  • Mark, Fabian, Enzo, Kozu-kun at Kamioka Mon-Wed.

Vacation Info

  • Mark 12/22-1/3
  • Enzo, 12/21-12/27 (but not 12/28)

  • Fabian 12/22-1/5
  • Hirata-san 12/21-22 (conference)
  • Shoda-san 12/18-21

Type-Bp (Shoda)

Past week report

  • PR3 slipped so often during the IM adjustment -> optic was fixed to the RM.

Plan for coming weeks

OMMT & OSTM (Ohishi)

Past week report

Plan for coming weeks

Watchdog system (Tanaka)

Past week report

  • Retest in Mitaka.-->There is no problem in operation test at all(The result is the same this week as well!!).

  • Start ordering mass production version.-->Ongoing(Formal request for quotation from the vendors.).

    • Waiting for arrival of mailing(by paper quotation).

Plan for coming weeks

  • Plan the operation test again at KAGRA-->

    • Actual test of WD operation(Retest).
    • The next on site test of the WDS: From 12/12(Tue) - 14(Thu) 11th:In Toyama,12th-14th:Kamioka,15th:Preparation day(Toyama->Tokyo).

Other site works

Safety

  • Incidents:
  • Foreseen risks
    • Type-A:
    • Type-B:
    • Type-Bp:

Discussion

2nd Brainstorming on how to exchange the payload part without completely disassembling the suspension chain

What to do with the Type-Bp tilt change ?

Travel Plans

  • Travel (Week of 12/11):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):
  • Travel (Week of 12/18):
    • Takahashi:
    • Okutomi:
    • Sato:
    • Ishizaki:
    • Mark:
    • Fabian:
    • Hirata:
    • Enzo:
    • Shoda:
    • Ohishi:
    • Fujii:
    • Tanaka:
    • Kozu (ICRR):
    • Arai (ICRR):

Next meeting

On 2017/12/15(Fri) from 15:00 @ Control Room