Agenda/Minutes of the VIS Meeting on 2019/11/15

2019/11/15 14:00 -

Zoom Meeting

Participants:

VIS Commissioning Task List

Post-O3 task list Procurement list in 2019FY

Progress report

Type-A

Past week report

Plan for coming weeks

Type B

Past week report

Plan for coming weeks

Type-Bp

Past week report

Plan for coming weeks

OMMT & OSTM

Past week report

  • The OSTM mirror is ready with first-contact.

Plan for coming weeks

  • Installation of the OSTM suspension is planed in the end of November.

VIS electronics

Past week report

Plan for coming weeks

Other site works

Safety

  • Incidents:

Discussion

  • Talk in JPS/ASJ meeting.

Travel Plans

  • Travel (Week of 11/18):
    • Takahashi:
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:
  • Travel (Week of 11/25):
    • Takahashi: 27-28
    • Sato:
    • Hirata:
    • Shoda:
    • Fujii:
    • Tanaka:

Next meeting

On 2019/11/22(Fri)