 * Working on the Type-A situation reproduction, which was assigned at cryo-payload upgrade review. (Shoda)

Agenda/Minutes of the VIS Meeting on 2020/5/29

2020/5/29 14:00 -

Zoom Meeting

Participants:

Task list towards O4

Schedule towards O4

Progress report

General

Type-A

  • As reported by Yamamoto-san ( see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14432) F1 GAS output was satured. So Yesterday I offloaded the GAS output by changing the offset on F1 and F2 (see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14434)

  • I took advantage of the suspended mode of KAGRA to investigate some strange response of the geophone installed on the Type A suspension. The test has been done with EX geophone. Basically, I changed the cutoff of the calibration filter from 10 mHz to 3 mHz and I measured the TF= GEO/(LVDT*w). By moving back to 3 mHz the DC cutoff the phase shift is reduced a lot, but the DC noise is growing up. I turned on the ID with blending at 140 mHz: the loop is stable, but the 148 mHz peack got excited (see klog http://klog.icrr.u-tokyo.ac.jp/osl/?r=14443).

Type-B

  • I worked in the measurements of the decay times of SR2. I still have to analyze data. No results to show yet.
  • Washimi-san reported the feedback signal in SRM F0 was too high. I offloaded onto the fishing rod this morning (klog entry 14436). According to the VIS wilki fishing rod page, this fishing rod does not suffer of any known problems.

  • I will postpone asking questions about inertial damping again for next week.

Type-Bp

Type-C

Controls

  • Working on the Type-A situation reproduction, which was assigned at cryo-payload upgrade review. (Shoda)

Electronics

Post O3

  • KAGRA is still in the suspended mode. Only remote measurements are available until May 31st (Q-measurement by Fabian, Type-A measurement by Lucia).
  • More activities in the control room and the site will be available from June 1st (Noise budget by Ushiba).
  • Decision for O3c in Virgo will be done within two weeks (from EO). If O3c was decided, task for O3c will be available as well (e.g. Sensor correction for SRs).
  • Post Obs. task has priority higher than task for O3c. Two weeks, at least, in June will be assigned for Post Obs. task.
  • The site work towards O4 will be rescheduled.

Post Obs. task (Request), Task for O3c (Plan, Sheet).

Safety

Discussion

  • Papers
    • Mechanics of Type-A tower + Cryo-payload: Shoda (on going)
    • Performance of Type-A: Lucia
    • Control of Type-A: Lucia?
    • Control (Sensor correction): Fujii
    • Type-B: Fabian (on going)
  • Personnel towards O4
    • Takahashi supervises both teams.
    • Type-A team: Sato, Miyo, Takahashi, company person
    • Type-B/Bp team: Shoda(supervisor), Hirata, Fabian, Terrence, Washimi, company person

Travel Plans

Next meeting

  • On 2020/6/5(Fri)