= Agenda/Minutes on 2021/1/8 = [[https://zoom.us/j/203743987|Zoom Meeting]] = CRY+VIS Interface Meeting = 13:30-13:55 Participants: Takahashi, Hirata, Sato, Yano, Aso, Miyo, Ushiba, Tomaru, Ikeda, Kimura, Hagiwara [[http://gwwiki.icrr.u-tokyo.ac.jp/JGWwiki/KAGRA/Upgrades/PostO3Upgrades|Post O3 Upgrade portal]] * Schedule for IX: Connection of ITMX was scheduled on 2/9. * Schedule for IY: Cooling of payload is scheduled from 1/12. * Schedule for EX: Let's discuss in the next time. * Corrugate tube fixing jig: Re-measurement at the beginning of March in IYV is planed. * Commissioning in vacuum: * Acceptance check items: * Jig for FC painting: Under manufacturing. * PF actuator: by the end of January. = VIS Meeting = 14:00-15:00 Participants: Takahashi, Tanaka, Fabian, Sato, Hirata, Aso, Miyo, Washimi == Progress report == === General === === Type-A === * Remedy work in IXV. * Replaced three blades for TF. * Mounted the ballast weight on the top plate of TF keystone. * Assembled and tested the limit switches for the yaw and vertical FR. * Assembled the geophones into the pods. === Type-B === Albums * [[https://photos.app.goo.gl/YiRfy6a9uDf4rvcKA|BS remedying work after O3]] * [[https://photos.app.goo.gl/4cvWnXCdCsf9WiYf7|SR2 remedying work after O3]] * [[https://photos.app.goo.gl/X2eaBxsZGaRHYAQK6|SR3 remedying work after O3]] * [[https://photos.app.goo.gl/6C5tGpn7CLgGUG9y6|SRM remedying work after O3]] Week of the 4th of January SR3 * In order to answer the question whether we should move the assembly frame next to SR3 as a back up plan, * We opened SRM chamber -X door, next to where the frame is now and * We measured the width of the clear space: 66 cm, which is enough. * We should ask Mirapro to move the frame, but * We need to move the rack with electronics and the cables and we need to allocate time to do it. * The IP stepper motor shaft pitch was measured to be 1.0 mm/thread. BS * The IP stepper motor shaft pitch was measured to be 0.8 mm/thread. * We received special screws, we installed the IP LVDTs and calibrated them: I have not checked the data but we might need to optimize the LVDT cards and repeat the calibration. I need to think about this issue more carefully. * Before removing IP immobilizing jig we measured the output of the LVDTs in order to recover the aligned position. * We replaced the heavy F0 top plate of the keystone assembly by a lighter one with ballast mass. * We installed the F0 yaw stepper motor with limit switches. Test pending. * We installed the F0 fishing rod limit switches. Test pending. Type-B all We checked the flanges we could use for the cables of a thermistor. See details in klog [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15700|15700]]. === Type-Bp === * If travel for Kamioka was limited, remedy work in PR3 would be postponed to February. === Type-C === === Controls === === Electronics === * Made the ver.2 LVDT combiner circuit. Preliminary result showed enough attenuation. The circuit board will be sent to Kamioka in the next week. == Towards O4 == * Type-B remedy work is on going. * Remedy work in IXV was started. Type-A team will go to installation in EYV parallelly. * Schedule. * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11475|Chart]] * Procedure documents. * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=5500|Type-A tower installation]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11598|Limit switches]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11520|Limit switch connecting guide]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11978|Replacement of TF blades]] * [[https://gwdoc.icrr.u-tokyo.ac.jp/cgi-bin/private/DocDB/ShowDocument?docid=11878|Wire gluing in PR3]] * [[https://onedrive.live.com/?authkey=!AOLVVVKJ_Zpn-2c&cid=1447B05D5B571A84&id=1447B05D5B571A84!26691&parId=1447B05D5B571A84!26683&o=OneUp|Type-B remedying work]] * Criteria in the acceptance test. * [[https://www.dropbox.com/s/6bv15yy6hg0wn40/Acceptance%20Test%20Documentation.docx?dl=0|Inspection document (sample)]] == Safety == == Discussion == == Travel Plans == The week from 1/11 * Takahashi: -1/15 * Sato: -1/15 * Hirata: -1/15 * Yano: -1/15 The week from 1/18 * Takahashi: ? * Sato: 1/18-22 * Hirata: ? * Yano: 1/18-22 == Next meeting == * On 2020/1/15(Fri)