Line 3: Line 3:
= Agenda/Minutes on 2021/2/12 = = Agenda/Minutes on 2021/2/19 =
Line 7: Line 7:
13:30-13:55 13:30-
Line 12: Line 12:
 * Schedule for IX: Release is scheduled on 2/18.  * Schedule for IX: Released on 2/18. BF is overload.
Line 17: Line 17:
 * Commissioning in vacuum: Closing of DN800 flange is available within a half of day.  * Commissioning in vacuum:
Line 20: Line 20:
 * Jig for FC painting: Delivered.  * Jig for FC painting: Assembling.
Line 23: Line 23:
14:00-15:30 14:00-
Line 28: Line 28:
'''EY'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15993|15993]] Setup of F2 , __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15997|15997]] Comment, __ryutaro.takahashi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16023|16023]] Comment , __ryutaro.takahashi__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16034|16034]] Comment , __ryutaro.takahashi__
'''General'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15737|15737]] We investigated the network connection. , __satoru.ikeda__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16028|16028]] Comment, __satoru.ikeda__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16038|16038]] Initialize the OSEMINF filters for all Type-Bp suspensions , __kouseki.miyo__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16040|16040]] Comment, __kouseki.miyo__
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16036|16036]] Cabling for temperature control equipment , __satoru.ikeda__
'''MCF'''
 * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16041|16041]] Recovery of IMC suspension , __ryutaro.takahashi__
'''PR3'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15889|15889]] Traverser motor test and cabling. , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16001|16001]] Comment, __satoru.ikeda__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16027|16027]] Comment , __satoru.ikeda__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15976|15976]] Picomotor of PR3_BF_T(Motor2) got stuck , __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16000|16000]] Comment, __satoru.ikeda__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16024|16024]] Comment , __fabian.arellano__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16026|16026]] Comment , __satoru.ikeda__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16032|16032]] Comment , __fabian.arellano__
'''PRM'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=9449|9449]] PRM glitch investigation: , __koki.okutomi__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15995|15995]] Comment, __shinji.miyoki__
'''SR3'''
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=15963|15963]] IM ballast mass adjustment , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16009|16009]] Comment, __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16007|16007]] Ballast mass adjustment on top of BF , __fabian.arellano__
  * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16018|16018]] Comment, __fabian.arellano__
  * (!) [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16035|16035]] Comment , __fabian.arellano__
 * [[http://klog.icrr.u-tokyo.ac.jp/osl/?r=16007|16007]] Ballast mass adjustment on top of BF , __fabian.arellano__
Line 52: Line 84:
The week from 2/22

 * Takahashi: 2/23-2/28
 * Sato: 2/23-26
 * Hirata: 2/23-26
 * Yano: 2/23-26

The week from 3/1

 * Takahashi: 3/1-5
 * Sato: 3/1-5
 * Hirata: 3/1-5
 * Yano: 3/1-5
Line 54: Line 99:
 * On 2020/2/zz(Fri)  * On 2020/2/26(Fri)

Agenda/Minutes on 2021/2/19

Zoom Meeting

CRY+VIS Interface Meeting

13:30-

Participants: Post O3 Upgrade portal

  • Schedule for IX: Released on 2/18. BF is overload.
  • Schedule for IY: Disconnection is scheduled on 3/11.
  • Schedule for EX: Connection is scheduled in the week of 3/15.
  • Corrugate tube fixing jig: Re-measurement is planed in 2/26-3/1 at IYV.
  • Commissioning in air: Commissioning of IX will be started. Other schedule has not been decided yet.
  • Commissioning in vacuum:
  • Acceptance check: Cryo-payload in IX and Type-A tower in EY are on going.
  • PF actuator: Not evaluated in IX, but after the commissioning for suspension.
  • Jig for FC painting: Assembling.

VIS Meeting

14:00-

Participants:

Progress report

EY

  • 15993 Setup of F2 , ryutaro.takahashi

    • 15997 Comment, ryutaro.takahashi

    • 16023 Comment , ryutaro.takahashi

    • (!) 16034 Comment , ryutaro.takahashi

General

  • 15737 We investigated the network connection. , satoru.ikeda

    • (!) 16028 Comment, satoru.ikeda

  • (!) 16038 Initialize the OSEMINF filters for all Type-Bp suspensions , kouseki.miyo

    • (!) 16040 Comment, kouseki.miyo

  • (!) 16036 Cabling for temperature control equipment , satoru.ikeda

MCF

  • (!) 16041 Recovery of IMC suspension , ryutaro.takahashi

PR3

  • 15889 Traverser motor test and cabling. , fabian.arellano

    • 16001 Comment, satoru.ikeda

    • (!) 16027 Comment , satoru.ikeda

  • 15976 Picomotor of PR3_BF_T(Motor2) got stuck , satoru.ikeda

    • 16000 Comment, satoru.ikeda

    • 16024 Comment , fabian.arellano

    • (!) 16026 Comment , satoru.ikeda

    • (!) 16032 Comment , fabian.arellano

PRM

  • 9449 PRM glitch investigation: , koki.okutomi

    • 15995 Comment, shinji.miyoki

SR3

  • 15963 IM ballast mass adjustment , fabian.arellano

    • 16009 Comment, fabian.arellano

  • 16007 Ballast mass adjustment on top of BF , fabian.arellano

    • 16018 Comment, fabian.arellano

    • (!) 16035 Comment , fabian.arellano

  • 16007 Ballast mass adjustment on top of BF , fabian.arellano

Electronics

Control

Towards O4

Safety

Discussion

Travel Plans

The week from 2/22

  • Takahashi: 2/23-2/28
  • Sato: 2/23-26
  • Hirata: 2/23-26
  • Yano: 2/23-26

The week from 3/1

  • Takahashi: 3/1-5
  • Sato: 3/1-5
  • Hirata: 3/1-5
  • Yano: 3/1-5

Next meeting

  • On 2020/2/26(Fri)

KAGRA/Subgroups/VIS/VISMinutes20210219 (last edited 2021-02-20 09:40:40 by RyutaroTakahashi)