Contents
Agenda/Minutes
CRY+VIS Interface Meeting
Date: 2021/9/17 13:00-
Participants:
Schedule
- IX: Health check. Investigation of the disturbance.
- EX: Health check. Installation of ACCs will be scheduled after the health check.
- IY: Some cables were repaired.
- EY: FR range was measured.
Status
- TM height setting: Summary of adjustable height range.
- Commissioning in air: Health check.
- Commissioning in vacuum:
- Overall commissioning:
- Acceptance check:
- PF actuator: At the in-vacuum commissioning.
- New vacuum pumps for V-chambers:
- Heater control: Implemented to BS and SRs.
Discussion
VIS Meeting
Date: 2021/9/10 14:00-
Participants:
Summary Report
Type-A
- Checked the adjustable height range in EY.
Type-Bp
Type-B
Type-C
Electronics
Control
Schedule
See Schedule
- Type-A team: Health check in IX and EX.
- Type-B team:
Milestone
- IMC suspensions are ready in air [40] will finish 2021/04/21. 
- PRs are ready in air [643] will finish 2021/07/09. 
- ETMX is ready in air [656] will finish 2021/08/25. 
- ITMX is ready in air [657] will finish 2021/08/31. 
- ETMY is ready in air [658] will finish 2021/09/16. 
- ITMY is ready in air [659] will finish 2021/11/08. 
- BS is ready in air [691] will finish 2021/11/24. 
- SRs are ready in air [663] will finish 2021/12/20. 
- Output suspensions are ready in air [695] will finish 2021/12/21. 
- TMSY is ready in air [708] will finish 2021/??/??. 
- TMSX is ready in air [684] will finish 2021/??/??. 
2021/03/29 updated
Safety
Discussion
Travel Plans
The week from 9/20
- Hirata: 9/21-22
- Yano: 9/21-22
The week from 9/27
- Takahashi: 9/27-10/1
- Sato: 9/27-10/1
- Hirata: 9/27-10/1
- Yano: 9/27-10/1
Next meeting
- 2021/9/24(FRI)