Line 31: Line 31:
 * Heater control: Test in IXV/EXV is planed. Repaired power controller will be delivered soon.  * Heater control: Test in IXV/EXV is planed. Repaired power controller will be delivered on 1/17.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2022/1/14 13:00-

Participants:

Post O3 Upgrade portal

Schedule

  • IX: Health check. Glitch in the F3 signals.
  • EX: Health check.
  • IY:
  • EY: Alignment. Preparation for ACCs.

Status

  • Replacement of flip cables: SRM was finished. Cables for Type-C will be delivered in the end of Jan.
  • TM height setting: ITMY.
  • Oplev: Setup of the TM Oplev in IY after the TM alignment.
  • ACC: Preparation for EY.
  • Commissioning in air: Return of GRY. Alignment of SR3/ETMY.
  • Commissioning in vacuum:
  • Overall commissioning:
  • Acceptance check:
  • PF actuator: At the in-vacuum commissioning.
  • New vacuum pumps for V-chambers: Cabling of the power line in IXV/EXC on 1/11-12.
  • Heater control: Test in IXV/EXV is planed. Repaired power controller will be delivered on 1/17.
  • Power source for Oplev:

Discussion


VIS Meeting

Date: 2022/1/14 14:00-

Participants:

Summary Report

Type-A

  • Preparing for the ACCs in EY. The tuning of the resonant frequency was finished.
  • Fixed the cables around the IP in EY.

Type-B

Type-Bp

Type-C

Electronics

Control

Schedule

See Schedule

  • Type-A team: Preparation for the ACCs in EY, Heter test in IXV/EXV
  • Type-B team:

Safety

Discussion

Travel Plans

(Date in Kamioka)

The week from 1/17

  • Takahashi: 1/18-21
  • Sato: 1/18-21
  • Hirata: 1/18-21

The week from 1/24

  • Takahashi: 1/24-28
  • Sato: 1/24-28
  • Hirata: 1/24-28

Next meeting

  • 2022/1/21(FRI)