Date: 2023/6/9 13:00- Date: 2023/6/9 13:00-13:15
Line 10: Line 10:
Participants: Participants: Takahashi, Mitsuhashi, Uchiyama, Ushiba, Ikeda, Miyoki, Hirata, Yokozawa, Kimura, Tomaru, Akutsu
Line 18: Line 18:
 * Type-C: Change of the watchdog threshold in OMMT1, OMMT2, and OSTM  * Type-C: Change of the watchdog threshold to 5000 in OMMT1, OMMT2, and OSTM
Line 24: Line 24:
 * Vacuum system:  * Vacuum system: Planning the replacements of the TMP in SR2 and the HV connector for ISP in IXA.
Line 27: Line 27:

== Post O4a ==
 * Measurements of the DAC noise.
 * Measurements on the sensor correction in SR2.
 * Optimization of the damping control in PRs.
 * IP control with the ACCs.
 * In-vacuum accelerometer for IOO: PEM started the preparation.
 * Hight adjustments of Type-A in the cooling.
 * Measurement of the drum-head modes.
 * Check of the length Oplev.
 * Check of the sensor noise in the cryo-payloads.
 * Temperature control for the Oplev: Preparing for the heater controller.
 * Check of the space in the IMMT chamber.

Agenda/Minutes

Zoom Meeting


CRY+VIS Interface Meeting

Date: 2023/6/9 13:00-13:15

Participants: Takahashi, Mitsuhashi, Uchiyama, Ushiba, Ikeda, Miyoki, Hirata, Yokozawa, Kimura, Tomaru, Akutsu

Acceptance check document

Suspensions

  • Type-A: Try of the tidal control in EX.
  • Type-B:
  • Type-Bp:
  • Type-C: Change of the watchdog threshold to 5000 in OMMT1, OMMT2, and OSTM

Other items

  • Oplev:
  • ACC:
  • Commissioning:
  • Vacuum system: Planning the replacements of the TMP in SR2 and the HV connector for ISP in IXA.
  • Heater control:
  • TMS:

Post O4a

  • Measurements of the DAC noise.
  • Measurements on the sensor correction in SR2.
  • Optimization of the damping control in PRs.
  • IP control with the ACCs.
  • In-vacuum accelerometer for IOO: PEM started the preparation.
  • Hight adjustments of Type-A in the cooling.
  • Measurement of the drum-head modes.
  • Check of the length Oplev.
  • Check of the sensor noise in the cryo-payloads.
  • Temperature control for the Oplev: Preparing for the heater controller.
  • Check of the space in the IMMT chamber.

Discussion


VIS Meeting

Date: 2023/6/9 10:00-11:00

Participants: Takahashi, Ushiba, Aso, Hirata

Summary Report

Type-A

Type-B

Type-Bp

Type-C

Electronics

Control

R&D

Schedule

  • O4a until 6/21.

Safety

Discussion

  • Towards O5
    • 30mHz IP for Type-A (Remote stopper): What is merit? Simulation is necessary.
    • Remote adjuster of F1 damper for Type-A/B: Height adjustment at BF is more important.
    • H4 geophone for Type-B
    • Accelerometer for Type-B: Manufacturing is ongoing in ATC.
    • BF damper for Type-B: Design to avoid reinstallation of the tower.
    • Wide range OSEM for Type-B/Bp: Priority is not high.
    • Improvement of the Type-C suspension: 1-3Hz vibration made a jump in pitch. KFC suspension with size variation can be available.
    • In-vacuum camera
    • Damping of Type-Bp suspension: Test after O4a.
    • Active isolation table for IOO beyond O5

Next meeting

  • 2023/6/23 10:00-