Differences between revisions 38 and 39
Revision 38 as of 2016-06-13 16:32:50
Size: 5355
Comment:
Revision 39 as of 2016-07-25 10:30:07
Size: 5354
Comment:
Deletions are marked like this. Additions are marked like this.
Line 38: Line 38:
== Adgenda == == Agenda ==

ISC Meeting on 2016/6/13 14:00 - 15:00

eZuce: http://srn.ezuce.com/joinSRN?meeting=MvM2Ml2I2BDIDI9I98De9v

Participants: Y. Michimura, K. Arai, E. Hirose, H. Yamamoto, T. Akutsu, K. Kokeyama, Y. Aso

Minutes

  • Members updated: Members

  • bKAGRA Phase 1 optical configuration study
    • Motivation for 3-km PRMI?
      • To check RoC and positions of PR mirrors
        • Even if PR2/3 are shifted by 1 cm each
        • Independent measurement of RoC with a mirror alone should be done also
        • Check if reference spheres for PR mirrors are available at Caltech [Hirose]

          • It's not easy to measure the RoC since we don't have reference spheres
          • Situation is even worse for IMMT1/2
      • To make 3-km long cavity to do FSS and to attract people
        • Check if IMC length stability and others are compatible with 3-km PRMI [Michimura]

      • To check thermal state of mirrors
    • Is dummy payload feasible?
      • ETM dummy payload is a single pendulum without any actuators (being prepared by VIS Type-A team)
        • Yaw could be damped with actuators on the last bottom filter, but not pitch
        • Check if dummy payload is quiet enough to make PRMI [Michimura]

      • Continue checking dummy ETM availability [Hirose]

        • Dummy ETM should be suspended in the way that we can reuse them afterwards
  • bKAGRA Phase 1 initial alignment / commissioning plan
    • Time it takes to check suspension performance not included in the plan
    • Possibility of faster CRYp instead of making dummy payload?
  • bKAGRA Phase 1 analog electronics request for AEL
    • Request to AEL [Michimura]

    • Assign people to modify/produce some of the electronics [Michimura]

      • Quad IQ Demodulator heat-up issue
      • Remake IQ Demodulator LSC to ASC for IMC WFS
      • Assemble RF Distribution Amplifier
      • RF Patch Panel modification
  • Announce Optickle seminar to broader community [Michimura]

Agenda

  • MIF membership [Michimura]
  • bKAGRA Phase 1 optical configuration study [Aso]: JGW-G1605199

    • BS angle changes slightly (0.0187 deg) -> OK

    • beam spot on PR3 shifts by 5 mm -> OK

    • move PR2 and PR3 1 cm each to stabilize PRC -> OK

    • HOM structure / LSC / ASC check -> to be done [Michimura]

    • room temperature ETM availability -> ? [Hirose]

    • any others?
  • bKAGRA Phase 1 initial alignment / commissioning plan [Michimura]: JGW-T1605274

    • 4 months (2017.6-9) for 300 K PRMI with dummy payload, 1 week (2018.1) for CRYp PRMI before cooling down
    • seems like we have enough time for ISC (but no margin)
    • everything should be ready by 2017.5, and most of the commissioning should be done by 2017.10
  • bKAGRA Phase 1 analog electronics request for AEL (Analog Electronics for ISC) [Michimura]

    • Quad IQ Demodulator LSC: 7 for full bKAGRA (5 in stock)
      • is heating problem solved? [AEL]
    • Quad IQ Demodulator ASC: 22 for full bKAGRA (0 in stock)
    • RF Distribution Amplifier: 10 for full bKAGRA (1 handmade in stock)
    • DC QPD Interface: 8 (+ AOS) for full bKAGRA (20 in stock) -> OK

    • Frequency Doubler: 2 for full bKAGRA (0 in stock)
    • Common Mode Servo Board?: 4 for full bKAGRA (1 in stock)
      • could be used for FSS using PRCL
      • slow output too noisy, Excitation B OUT 2 is strange, power switch
    • RF Patch Panel modification (too thick to fasten nuts) [Miyo?]
    • RF PD modification (Dsub 9pin won't fix tight, breaks easily with single power supply) [Doi?]
    • single-ended to differential, differential to single-ended: 10 each being prepared by AEL -> OK


  • bKAGRA optical layout around PRC [Aso]
    • POY beam is clipped by PR3 optical bench suspension wire
    • JGW-T1605261 (cartoon)

  • iKAGRA post-run calibration mystery [Aso]
  • Requirement for the noise of watchdogs for coil drivers [Aso]
  • Viewport quality for GV between SRM and OMMT [Akutsu]
  • bKAGRA ISC cabling [Michimura/Doi]
    • Doi-san said he will help.
  • Mirror absorption measurement status [Hirose]
  • OMC status [Somiya]
  • Magnetic noise, actuator noise calculation for cryogenic payload [Michimura]
  • Task list update (TaskList) [Michimura]

Next meeting

2016/6/27 14:00 - 15:00

back to Meetings page

KAGRA/subgroup/ifo/MIF/Minutes20160613 (last edited 2016-07-25 10:30:07 by YutaMichimura)