Differences between revisions 21 and 22
Revision 21 as of 2018-10-09 18:38:49
Size: 2278
Comment:
Revision 22 as of 2018-10-09 18:39:22
Size: 2302
Comment:
Deletions are marked like this. Additions are marked like this.
Line 24: Line 24:
 * Interlock repairing

Detailed task list of PCal is listed here.

X-end PCal

Urgent

  • RxPD1 repairing
    • 2 ICs seems broken. ICs have arrived at Kamioka.
  • OFS2 closed loop functionality repairing
    • Register is missing. To be delivered.
  • Interlock repairing

2nd-urgent

  • Laser remote control
    • Setup done. LAN cable should be replaced to shorter one.
  • Stray light
    • Put dumpers

~10/20 first test to inject PCal laser to the X-end test mass

  • Rx module alignment
  • AOM response measurement
    • Check working point is consistent to that in KEK
  • OL/CL TF measurement
  • WSK measurement
    • Modification is required from LIGO's procedure.
    • Code for WSK measurement analysis
    • To be delivered on 9/19 or 20 to Toyama Univ.
    • May have to prepare voltage calibrator to calibrate readout by DGS.

~X-arm commissioning line injection

  • BPM test
    • Picomoter setting
  • Preparation for X-arm commissioning calibration line injection

~O3

  • RPN measurement
  • Laser noise measurement
  • Harmonics noise measurement
  • VGA noise measurement
  • Excitation noise measurement
  • Peak stability test
  • Shot noise
  • Offset input noise
  • Noise model
  • Unstable D-sub connection at Tx module
    • Some connectors are dead.
  • Cable arrangement
  • OFS upgrade
  • Operation tool preparation

Bonus work

  • AOM current
    • Sometimes over 0.5 V ?
  • Take care about grounding
  • Initial laser power just after turned on seems too small ?

Pre-categorization

Y-end PCal

Laser power calibration setting in Toyama Univ.

PcalTask (last edited 2018-11-22 09:41:33 by chihiro.kozakai)