== Period == . ~+October 2008 - December 2008+~ |
|
Line 12: | Line 15: |
|| 実験室の冷却 || 三代木 || || 2008/12/End || || レーザーの冷却 || 三代木、内山 || || 2008/12/End || || レーザーブースのクリーン化 || 三代木 || || 2008/12/End || == Small Tasks & Schedules == || '''Task Name''' || '''Responsible''' || '''STATUS''' || '''due''' || || [[CLIO/Tasks/Damping|ダンピング]] || 内山 || 50% LSPI by Telada || 2009/09/End || || [[CLIO/Tasks/DigitalControl/AnalogFrontEnd2|デジタル化アナログフロントエンド・第2段]] || 辰巳 || 10% || 2009/07/End || || RF intensity noise investigation || 我妻 || || || || [[CLIO/Tasks/DigitalControl|デジタル化 1st phase]] || 宮川 || 50% shopping + shipping || 2009/09/End || || [[CLIO/Tasks/CoilBobbin|コイルボビン]] || 内山 || 75% @ 2009/06/15 || 2009/09/End || || [[CLIO/Tasks/EndLight|エンド光]] || 三代木 || 90% Inline End was done @ 2009/06/15 || 2009/06/End || || [[CLIO/Tasks/CoilDriver|アクチュエイター雑音低減・第1段]] || 辰巳 || not yet installed || 2009/03/End || || [[CLIO/Tasks/DigitalControl/AnalogFrontEnd|デジタル化アナログフロントエンド・第1段]] || 辰巳 || Done || 2009/03/End || || [[CLIO/Tasks/Done/BeamCenterJig|粗調ビームセンターリング]] || 新井 || design due: 2009/01/08, deliver due 2009/01/End, preparation ends 2009/02/06 || 2009/03/End || == Pending Tasks == || '''Task Name''' || '''Responsible''' || '''COMMENTS''' || || BS pendulum modification || 三代木 || || || ST pendulum modification || 三代木 || || || [[CLIO/Tasks/RecoilMass|リコイル・マス]] || 寺田 || || || MC WFS and beam orientation control || 我妻 || || || Arm cavity WFS or dithering || 我妻 || 優先度:高 Dithering 相当のシステムを早急に構築する必要あり。 || || Main suspension Y-stage installation || 内山 || || || [[CLIO/Tasks/CoilDriver|アクチュエイター雑音低減・第2段]] || 辰巳 || コイルアクチュエイター効率の低減 || || Up-conversion noise investigation || 新井 || || || Shadow sensor || 辰巳、高橋 || || == Past small Tasks == || '''Task Name''' || '''Responsible''' || '''STATUS''' || '''due''' || |
|| レーザーブースのクリーン化 || 三代木 || not yet finished @ Dec 2008 || 2008/12/End || || Laser LD exchange || 日本レーザー || 悪夢の始まり ... || 2008/11/11 || ---- ||<#FF0000> '''~+常温感度達成!+~''' || All || 2008/11/06 || || Violin mode Q measurement || 内山 || [[http://gw.icrr.u-tokyo.ac.jp:8888/clio_blog/2008/11/081106-violin-mode-q-measurement.html|blog 081106]] || 2008/11/06 || || 常温感度 Noise Budgeting || 内山、三代木、新井、辰巳 || 10/27 - 30 || 2008/10/End || || Perkin Elmer 2mm PD || 三代木、辰巳 || [[http://gw.icrr.u-tokyo.ac.jp:8888/clio_blog/2008/10/rf-pd-test.html|雑音評価]] || 2008/12/End || || NiP 散乱光吸収板 + 2mm PD || 三代木、内山 || 10/17 2mm PD 交換 + NiP 設置 [[http://gw.icrr.u-tokyo.ac.jp:8888/clio_blog/2008/10/081017.html|blog 081017]] || 2008/10/End || || レーザー不調 || 内山 || 1W 出力 -> 300mW MC 入射 || Laser LD 交換へ || |
Period
October 2008 - December 2008
Top-priority
- マイルストーン: 常温での熱雑音感度の達成
- 熱雑音感度検証作業
Main Tasks
Task Name |
Responsible |
STATUS |
due |
レーザーブースのクリーン化 |
三代木 |
not yet finished @ Dec 2008 |
2008/12/End |
Laser LD exchange |
日本レーザー |
悪夢の始まり ... |
2008/11/11 |
常温感度達成! |
All |
2008/11/06 |
|
Violin mode Q measurement |
内山 |
2008/11/06 |
|
常温感度 Noise Budgeting |
内山、三代木、新井、辰巳 |
10/27 - 30 |
2008/10/End |
Perkin Elmer 2mm PD |
三代木、辰巳 |
2008/12/End |
|
NiP 散乱光吸収板 + 2mm PD |
三代木、内山 |
10/17 2mm PD 交換 + NiP 設置 blog 081017 |
2008/10/End |
レーザー不調 |
内山 |
1W 出力 -> 300mW MC 入射 |
Laser LD 交換へ |