= CLIO Project = ||[[CLIO|PROJECT]] ||[[CLIO/Meeting|MEETING]] ||[[CLIO/Plans|SCHEDULES&TASKS]] ||[[CLIO/Technical|TECHNICAL]] ||[[CLIO/Links|LINKS]] ||[[CLIO/HowTo|HOWTO]] || ---- |
|
Line 17: | Line 12: |
* [[CLIO/Plans/CoilBobbin|コイルボビン (担当:鈴木、内山) due: 200X/XX/XX]] | * [[CLIO/Plans/CoilBobbin|コイルボビン]] (担当:内山) 75% done @ 2009/06/15 / due: 2009/09/End |
Line 24: | Line 19: |
* BS pendulum modification (担当:三代木) start:2009/06 * ST pendulum modification (担当:三代木) start:2009/06 |
|
Line 28: | Line 25: |
* BS pendulum modification (担当:三代木) * ST pendulum modification (担当:三代木) |
|
Line 40: | Line 35: |
---- ||[[CLIO|CLIO wiki Top]]||[[LCGT|LCGT wiki Top]]|| |
Current top-priority tasks
マイルストーン: 常温での熱雑音感度の達成
- 熱雑音感度検証作業
マイルストーン: 低温での常温感度再現
- 低温化準備作業
マイルストーン: 低温での常温感度再現
- 低温時noise budget作成作業
Small Tasks & Schedules
コイルボビン (担当:内山) 75% done @ 2009/06/15 / due: 2009/09/End
- RF intensity noise investigation (担当:我妻)
- BS pendulum modification (担当:三代木) start:2009/06
- ST pendulum modification (担当:三代木) start:2009/06
Pending Tasks
- MC WFS and beam orientation control (担当:我妻)
- Arm cavity WFS or dithering (担当:我妻) 優先度:高Dithering 相当のシステムを早急に構築する必要あり。
- Main suspension Y-stage installation (担当:内山)
- Up-conversion noise investigation (担当:新井)
- Shadow sensor (担当:辰巳、高橋)
Past small Tasks