Archive of the Daily Commissioning Meeting at 1PM
Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM
Commissioning leader: Aso (July 17th-19th)
Afternoon
- ETMY HP coil driver check (Takahashi, Yamada)
- Watchdog, Output resistance, Cable resistance, Take a picture of the PCB
- Check the maximum current acceptable by the in-vac cable.
- Calculate theoretical limit (Ushiba)
- AS alignment (Kokeyama et al)
- SR3 OSEM check (Fabian, Terrence)
- Y-arm mass lock trial (SB, EY, MN, et al)
- ISS work (Yoshioka, Nakano)
Evening
- Y-arm mass lock trial (SB, EY, MN, et al)
- Type-A guardian work on ETMX (Kokeyama)
- DRMI investigation ? (SB, EY, MN, et al)
- Found Y end coil needed more range, more drive for MN (dominate 10Hz sensing noise limited, cross over)
Note
- DC feedback works perfect
- Tcam alignment system is done (see from camera screen)
- ALIGNED guardian on ETMX (test phase)
Morning
- HP coil driver modification ? (Yamada, Fabian, Terrence)