== Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM ==

== Afternoon ==
 * GV opened last night
 * ITMY release ongoing (CRY, VIS)
 * After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
 * Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
 * Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
 * Type-A common guardian
 * Oplev swap for IMMT2
 * Oplev swap for PR2 if possible with IFO
 
== Evening ==
 * Finesse measurement
 * Arm transition method commissioning


== Morning ==
 * Continued SRs study (Fabian)
 * IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)


=== We want a sensitivity monitor! ===
=== We want to plan Feedforward on typeA! ===
=== We want to decide the Commissioning strategy! ===

Note
 * IY chamber will be closed on Saturday


----

Archive of the Daily Commissioning Meeting at 1PM


Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM

Afternoon

  • GV opened last night
  • ITMY release ongoing (CRY, VIS)
  • After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
  • Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
  • Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
  • Type-A common guardian
  • Oplev swap for IMMT2
  • Oplev swap for PR2 if possible with IFO

Evening

  • Finesse measurement
  • Arm transition method commissioning

Morning

  • Continued SRs study (Fabian)
  • IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)

We want a sensitivity monitor!

We want to plan Feedforward on typeA!

We want to decide the Commissioning strategy!

Note

  • IY chamber will be closed on Saturday


Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM

Afternoon

  • GV opened last night
  • ITMY release ongoing (CRY, VIS)
  • After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
  • Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
  • Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
  • Type-A common guardian
  • Oplev swap for IMMT2
  • Oplev swap for PR2 if possible with IFO

Evening

  • Finesse measurement
  • Arm transition method commissioning

Morning

  • Continued SRs study (Fabian)
  • IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)

We want a sensitivity monitor!

We want to plan Feedforward on typeA!

We want to decide the Commissioning strategy!

Note

  • IY chamber will be closed on Saturday


Today's work plan: 2019/7/31 1PM - 2019/8/1 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • ITMY: BF work. (Okutomi, Sato, Fujii)
  • ITMY: H1 actuator investigation. (Ushiba, Yamada)
  • PEM: Reporting Temperature. (Yokozawa)
  • VAC, MIF: Opning GV, alingment. (Saito, Nakano, Michimura, Akutsu)
  • ASO: Small works at ETMX (Akutsu)
  • Replacing light source for IMMT2. (Akutsu)
  • Type B: Back to aligned mode. (Fabian)
  • DET: replacing OS of DET computer for offline analysis. (T.Yamamoto)
  • CAL: Xend Tcam will be touched. (Inoue)

Evening

  • IFO some work. (Nakano, Michimura, Akutsu)
  • VIS work can be done for Y arm work since Y arm is not available for a while. (Fujii, Okutomi)

Weekend

Morning

  • Releasing ITMY suspension. (Ushiba)
  • PSL work for grounding problem. (Nakano)
  • Maintenance for Ondotori at X-end (T.Yamamoto)


Today's work plan: 2019/7/30 1PM - 2019/7/31 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
  • Check H1 actuator. (Ushiba, Tomaru, Yamada)
  • ALS: Tuning returning beam at center area, and in PSL room shortly. (Enomoto, Sugimoto)
  • Connecting tube on the AS table. (Michimura)
  • ISS: work for servo in the PSL for 30min. (Yoshioka, Nakano)
  • AOS: Some small works in the center room for oplev. (Akutsu)
  • PEM: test a new sensor at IY0 rack. (Yokozawa, Washimi)
  • BS: measurement of noise. (Fabian)

Evening

  • IFO some work. (Nakano, Michimura, Akutsu)

Weekend

Morning

  • DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino)
    • VIS should go safe mode. (Fabian)
    • DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi)
  • Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
  • Connecting tube on the AS table. (Michimura)
  • AOS: Some small works at Y end for oplev. (Akutsu)
  • PEM: work around IYC chamber. (Yokozawa, Washimi)


Today's work plan: 2019/7/26 1PM - 2019/7/30 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • Monitor for venting ITMY (Okutomi)
    • Updating RT model for Type A, except for ITMY (Okutomi)
  • ASC test on ITMX (Ushiba)
  • ETMX work (Fujii)
  • SR3 work for control loop IM yaw (Fabian)
  • OMC characterization with control (Kokeyama, Somiya)
  • Fiber noise cancellation at control room(Enomoto, Sugimoto)
  • ISS put wind shield outside PSL (Yoshioka, Kukromiya)
  • Pick up Moku:Lab (Guiguo)

  • Stop venting around the evening (Ushiba)
  • Checking cable noise for PEM (T.Takana)
  • PEM: Vibration measurement at IXC (Yokozawa)
  • Measurement for PRs (Shoda)

Evening

  • Fiber noise cancellation (Enomoto)

Weekend

  • Fiber noise cancellation work at PSL on Saturday and Sunday(Enomoto, Sugimoto)
    • Changing optics for Yarm.
  • Venting again on Sunday morning (Ushiba)
    • Monitor for venting ITMY (Okutomi)
  • ETMX work on Saturday and Sunday(Fujii)

Monday Morning

  • SRs TF measurement, off load (Fabian)

Monday Aftenoon

  • SRs TF measurement, off load (Fabian)

Monday Evening


Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Fixing ITMY stuck (Okutomi)
  • ASC test on ITMX (Ushiba)
  • ETMX work (Fujii)
  • SR3 work for control loop IM yaw (Terrence)
  • Cabling for BIO this afternoon (Enomoto)
  • Xarm ALS hand over to IR using TR (Enomoto)
  • OMC characterization with control (Kokeyama, Darkhan)

Evening

  • Xarm ALS hand over to IR using TR (Enomoto)

Weekend

Morning

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • ITMX damping (Ushiba)
  • Cryo cooler valve exchange (Kimura, Ushiba)
  • SR3 TF measurement (Fabian)
  • Automation for SR3 and SRM (Shoda)
  • Noise source by cable or something in the center room (Yokozawa)
  • Setting magnet meter at Y end (Yokozawa)


Today's work plan: 2019/7/24 1PM - 2019/7/25 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Replacing LVDT driver on SR3(Fabian)
  • Single arm locking (Nakano)
  • Fix AC to stablize temeparute (Miyoki)
  • ITMY damping (Okutomi)
  • Maintenance for Ondotori (Yokozawa, T. Tanaka)
  • ALS model medication (Enomoto, Sugimoto)
  • MZ in PSL room for a hour (Guiguo)
  • OMC characterization with control (Kokeyama, Darkhan)

Evening

  • ALS hand over to IR using TR (Nakano, Enomoto)
  • DRFPMI lock (Nakano, Enomoto)

Weekend

Morning

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • SR3 OSEM check (Fabian, Terrence)
  • Automation for Suspensions except for SR3 (Shoda)


Standing issues

  • Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
  • Y-arm lock
    • ETMY suspension control
    • ITMY damping
      • One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  • DRMI lock stability
    • Model HOM-PHD signal distortion (Aso, Kokeyama)
    • Search for better Gouy phase in PRC
  • Initial alignment automation (Nakano)
  • IFO configuration Guardian (Kokeyama)
  • SDF for all the VIS (Shoda, Okutomi)
  • Type-A related
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Exchanging modified HPCD.
    • Type A: Feed forward technic to suppress extra motion (Nakano)
  • Type-B related
    • SR3 Yaw motion is too large (Fabian, Terrence)
  • Type-C related
    • OSEM characterization for OSTM (on going, Takahashi)
  • OMC
    • Check the OMC on the AS table
    • OMC characterization with control
  • Laser safety
    • Debug the laser safety guardian (Nakano)
  • IR QPD, centering on IR , green QPD at ETMY (Akutsu)
  • AS tube installation on 7/30-31 (Michimura)
  • Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
  • Fiber noise cancellation on Saturday (Enomoto, Sugimoto)


Today's work plan: 2019/7/23 1PM - 2019/7/24 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • PEM: 320.5Hz noise (Yokozawa)
  • Preparation for fiber noise cancellation (Enomoto, Sugimoto)
    • This turns on air filters.
  • OMC control (Kokeyama, Darkhan)
  • ALS hand over to IR(Stefan, Valera, Nakano)

Evening

  • ALS hand over to IR (Stefan, Valera, Nakano)
  • DRFPMI lock (Stefan, Valera, Nakano)

Weekend

Morning (Monday)

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • SR3 OSEM check (Fabian)
    • DGS maintenance for prm or srm.
  • Adding BIO card to k1als0, k1ioo1.
  • Exchanging old type modified HPCD. (Ushiba, Takahashi)
  • ISS control servo (Yoshioka, Kokeyama)


Today's work plan: 2019/7/22 1PM - 2019/7/23 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Exchanging HPCD(Fabian, Washimini)
    • check the range of new HPCD using oplev (Valera, Nakano).
  • ITMY damping (Okutomi)
  • ALS sweep to find IR resonance (MN, VF)
    • TEMP00 lock with dither(Nakano).

Evening

  • ALS sweep to find IR resonance (MN, VF)
  • DRMI lock (Stefan)

Weekend

Morning (Monday)

  • ITMY damping (Okutomi)
  • SR3 OSEM check (Fabian)
  • Type A: Feed forward technic to suppress extra motion (Nakano)


Today's work plan: 2019/7/19 1PM - 2019/7/22 1PM

Commissioning leader: Aso (19th), Miyakawa (22nd)

Afternoon

  • ALS sweep to find IR resonance (MN, VF)
  • Start X-End cryocooler (Yamada, TakahashiM)
  • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
  • ISS servo setup and OLTF measurement (Yoshioka, Kuromiya, Yamamoto)
  • Serial number check of OpLev SLDs (Yamada)

Evening

  • ALS sweep to find IR resonance (MN, VF)

Weekend

  • IFO configuration guardian (Kokeyama, Saturday)
  • Modification of the IMC servo (Enomoto, Sunday)
  • Transition to IR (Nakano, Valera, Sat & Sun)

  • TF measurement of Type-A (Yamada, Saturday morning)
  • ITM actuator efficiency measurement (Sun morning ?)

Morning (Monday)

  • SR3 OSEM check (Fabian)


Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM

Commissioning leader: Aso (July 17th-19th)

Afternoon

  • ETMY HP coil driver check (Takahashi, Yamada)
    • Watchdog, Output resistance, Cable resistance, Take a picture of the PCB
  • Check the maximum current acceptable by the in-vac cable.
    • Calculate theoretical limit (Ushiba)
  • AS alignment (Kokeyama et al)
  • SR3 OSEM check (Fabian, Terrence)
  • Y-arm mass lock trial (SB, EY, MN, et al)
  • ISS work (Yoshioka, Nakano)

Evening

  • Y-arm mass lock trial (SB, EY, MN, et al)
  • Type-A guardian work on ETMX (Kokeyama)
  • DRMI investigation ? (SB, EY, MN, et al)
  • Found Y end coil needed more range, more drive for MN (dominate 10Hz sensing noise limited, cross over)

Note

  • DC feedback works perfect
  • Tcam alignment system is done (see from camera screen)
  • ALIGNED guardian on ETMX (test phase)

Morning

  • HP coil driver modification ? (Yamada, Fabian, Terrence)