Differences between revisions 4 and 26 (spanning 22 versions)
Revision 4 as of 2019-07-22 12:58:43
Size: 1899
Editor: YoichiAso
Comment:
Revision 26 as of 2019-08-15 08:59:41
Size: 17174
Comment:
Deletions are marked like this. Additions are marked like this.
Line 3: Line 3:
----

== Today's work plan: 2019/8/9 1PM - 2019/8/15 1PM ==

=== Afternoon ===
 * Hunting ITMY big morion (Lucia)
 * Type A work (Fujii, Lucia)
 * Work for fiber cancelation for replacing power supply to avoid magnetic field of small DC power supply (Enomoto, Sugimoto)
 * SR3 TF measurement (Fabian)
 * Restarting DAQ at 5pm (Yamamoto)
 * PEM: measure vibration noise of pump (Yokozawa, Kaihotsu)
 * PEM: measure fiber noise for ALS (Washimi)
 * CAL: AOM will be tested from control room for Y end (Inoue)
 * ISS work outside PSL (Yoshioka, Kuromiya, Nakano)
 * Covering for TMS at ETMX (Akutsu)

=== Evening ===
 * Finesse measurement (Nakano)
 * IFO works with Yarm for FPMI (Nakano)
 * Work for fiber cancelation (Enomoto, Sugimoto)
 * Leave IFO locked from night to morning (Nakano)

=== Weekend ===
 * IFO works with Yarm (Nakano)
 * Work for fiber cancelation (Enomoto, Sugimoto)

=== Morning ===

----

== Today's work plan: 2019/8/8 1PM - 2019/8/9 1PM ==

=== Afternoon ===
 * Leak check at ITMY (Kimura)
 * Work for fiber cancelation (Enomoto, Sugimoto)
 * Measure TF of ITMY for top part by making health check list (Liucia)
 * Starting EY cry cooler (Kimura)
 * Put cover on TMSX at X end (Akutsu)
 * OSTM work (Takahashi)
 * CAL: Replacing AOM at ETMY, tuning camera at ETMY (Inoue)
 * SR3 TF measurement (Fabian)


=== Evening ===
 * Work for fiber cancelation (Enomoto, Sugimoto, Akutsu)
 * Some IFO work with Yarm (Nakano)
 * Leave IFO locked (Nakano)

=== Weekend ===

=== Morning ===
 * Stop ETMX cryo cooler (Kimura)
 * SR3 TF measurement (Fabian)
 * X fiber noise for temp. control (Enomoto, Sugimoto)
 * Type A work (Fujii, Lucia)
 * ISS servo in the PLS morning (Yoshioka)

----

== Today's work plan: 2019/8/7 1PM - 2019/8/8 1PM ==

=== Afternoon ===

 * Lock fiber cancelation, entering PSL and turning off filters (Enomoto, Sugimoto)
 * ISS work outside of PSL (Yoshioka, Nakano)

 * SR3 noise investigation (Fabian)
 * Measure TF of ITMY for top part by making health check list (Liucia)

 * OSTM work (Takahashi)
 * Exchanging IX oplev source (Akutsu)


=== Evening ===
 * One arm WFS test with X arm(Nakano)
 * Leave IFO locked (Nakano)

=== Weekend ===

=== Morning ===
 * X fiber noise control or temperate control for Y (Enomoto, Sugimoto)
 * SR2, 3 noise investigation (Fabian)
 * OSTM work (Takahashi)
 * Type A work (Fujii, Lucia)

----

== Today's work plan: 2019/8/6 1PM - 2019/8/7 1PM ==

=== Afternoon ===
 * Opening GV for ITMX (VAC)
 * ITMX oplev work before Finesse measurement (Yamada)

 * Finesse measurement for Xarm (Nakano)
 * Measure TF of ITMY for top and cryopayload by making health check list (Okutomi, Yamada)
 * OSTM work (Takahashi)
 * WFS centering at REFL (Nakano)
 * HDD installation for CAL PC (Darkhan)
 * Exchanging PC for VAC mon (Yokozawa)

=== Evening ===
 * One arm WFS test with X arm(Nakano)
 * Leave IFO locked (Nakano)

=== Weekend ===

=== Morning ===
 * Exchanging k1dc0 in early morning 8am (Yamamoto, Oshino)
 * Fiber cancelation work (Enomoto, Sugimoto)
 * ISS work in the PSL (Yoshioka)
 * SR2, 3 noise investigation (Fabian)
 * OSTM work (Takahashi)
 * Type A work (Fujii, Lucia)

----


== Standing issues 2019/8/5 ==

 * Sensitivity monitor for various DoF (CAL)
 * PEM - measured data sharing (Washimi, Yokozawa)
 * How to control the PSL temperature when people enters the room (Miyoki)

 * We need IFO commissioning strategy!!!
 * One arm WFS test
 * DRMI lock stability
  * 3f transition
  * Search for better Gouy phase in PRC
 * PRFRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
 * Arm: transition
  * Y-arm lock
 * Try ALS mass lock with FFUs and ACs turned off

 * Type-A related
  * Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
  * Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
  * United Guardian for all 4 suspensions (Okutomi)
  * Damping
  * Exchanging modified HPCD.
  * Type A: Feed forward technic to suppress extra motion (Nakano)


[[KAGRA/Commissioning/DailyMeetingArchive|Meeting archive]]


-----

<<Anchor(1PMMeetings)>>

== Today's work plan: 2019/8/5 1PM - 2019/8/6 1PM ==

=== Afternoon ===
 * Damping monitor (Okutomi, Lucia)
 * Finesse measurement for Xarm. (Nakano)
 * Damping work for Type A. (Fujii)
 * SR2, 3 noise investigation (Fabian)
 * Entering cleaning area for taking pictures (with Yokozawa)

 * Cabling ALS fiber noise cancellation (Enomonoto, Miyoki)
 * OSTM work for OSEM inve(Takahashi)

=== Evening ===
 * One arm WFS test (Nakano)

=== Weekend ===

=== Morning ===
 * Fix vacuum monitor (Yokozawa)
 * Increasing ITMX temperature (CRY)
 * Entering cleaning area for taking pictures (with Kokeyama)
 * SR2, 3 noise investigation (Fabian)
 * Installation circuit to ITMY, and control test (Yamada)
 * OSTM work (Takahashi)
 * Fixing k1IOO1 (Yamamoto)
 * IXV work (Fujii)
----


== Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM ==

=== Afternoon ===
 * GV opened last night
 * ITMY release ongoing (CRY, VIS)
 * After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
 * Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
 * Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
 * Type-A common guardian
 * Oplev swap for IMMT2
 * Oplev swap for PR2 if possible with IFO
 
=== Evening ===
 * Finesse measurement
 * Arm transition method commissioning


=== Morning ===
 * Continued SRs study (Fabian)
 * IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)


=== We want a sensitivity monitor! ===
=== We want to plan Feedforward on typeA! ===
=== We want to decide the Commissioning strategy! ===

Note
 * IY chamber will be closed on Saturday


----

== Today's work plan: 2019/8/2 1PM - 2019/8/5 1PM ==

=== Afternoon ===
 * ITMY problem investigation (CRY&VIS)
 * Finesse measurement (Nakano)
 * X-arm transition (Nakano)
 * ISS (Yoshioka)
 * ITMX Type-A control (VGAS oscillation) (Lucia)
 * PEM measurements around IFO REFL (Yokozawa)
 * ALS fiber noise cancellation (Enomonoto)

=== Weekend ===
 * Fiber noise cancellation
  * Turn off FFU, ACs

=== 8/5 Morning ===
 * ITMY pumping (VIS, CRY)
 * SR2, 3 noise investigation (Fabian)
 * DGS maintenance (Yamamomot, Oshio, Miyakawa)
   * dc0 replacement
   * Add BIO to k1ioo1
 * Installation of circuit to ALS (Enomoto)

----

== Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM ==


==== Afternoon ====
 * GV opened last night
 * ITMY release ongoing (CRY, VIS)
 * After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
 * Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
 * Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
 * Type-A common guardian
 * Oplev swap for IMMT2
 * Oplev swap for PR2 if possible with IFO
 
==== Evening ====
 * Finesse measurement
 * Arm transition method commissioning


==== Morning ====
 * Continued SRs study (Fabian)
 * IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)


=== We want a sensitivity monitor! ===
=== We want to plan Feedforward on typeA! ===
=== We want to decide the Commissioning strategy! ===

Note
 * IY chamber will be closed on Saturday

----

== Today's work plan: 2019/7/31 1PM - 2019/8/1 1PM ==
Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

=== Afternoon ===
 * ITMY: BF work. (Okutomi, Sato, Fujii)
 * ITMY: H1 actuator investigation. (Ushiba, Yamada)

 * PEM: Reporting Temperature. (Yokozawa)
 * VAC, MIF: Opning GV, alingment. (Saito, Nakano, Michimura, Akutsu)
 * ASO: Small works at ETMX (Akutsu)
 * Replacing light source for IMMT2. (Akutsu)
 * Type B: Back to aligned mode. (Fabian)
 * DET: replacing OS of DET computer for offline analysis. (T.Yamamoto)
 * CAL: Xend Tcam will be touched. (Inoue)

=== Evening ===
 * IFO some work. (Nakano, Michimura, Akutsu)
 * VIS work can be done for Y arm work since Y arm is not available for a while. (Fujii, Okutomi)

=== Weekend ===
 

=== Morning ===
 * Releasing ITMY suspension. (Ushiba)
 * PSL work for grounding problem. (Nakano)
 * Maintenance for Ondotori at X-end (T.Yamamoto)


----

== Today's work plan: 2019/7/30 1PM - 2019/7/31 1PM ==
Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

=== Afternoon ===
 * Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
 * Check H1 actuator. (Ushiba, Tomaru, Yamada)
 * ALS: Tuning returning beam at center area, and in PSL room shortly. (Enomoto, Sugimoto)
 * Connecting tube on the AS table. (Michimura)
 * ISS: work for servo in the PSL for 30min. (Yoshioka, Nakano)
 * AOS: Some small works in the center room for oplev. (Akutsu)
 * PEM: test a new sensor at IY0 rack. (Yokozawa, Washimi)
 * BS: measurement of noise. (Fabian)

=== Evening ===
 * IFO some work. (Nakano, Michimura, Akutsu)

=== Weekend ===
 

=== Morning ===
 * DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino)
  * VIS should go safe mode. (Fabian)
  * DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi)
 * Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
 * Connecting tube on the AS table. (Michimura)
 * AOS: Some small works at Y end for oplev. (Akutsu)
 * PEM: work around IYC chamber. (Yokozawa, Washimi)

----

== Today's work plan: 2019/7/26 1PM - 2019/7/30 1PM ==
Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

=== Afternoon ===
 * Monitor for venting ITMY (Okutomi)
  * Updating RT model for Type A, except for ITMY (Okutomi)
 * ASC test on ITMX (Ushiba)
 * ETMX work (Fujii)
 * SR3 work for control loop IM yaw (Fabian)
 * OMC characterization with control (Kokeyama, Somiya)
 * Fiber noise cancellation at control room(Enomoto, Sugimoto)
 * ISS put wind shield outside PSL (Yoshioka, Kukromiya)
 * Pick up Moku:Lab (Guiguo)
 * Stop venting around the evening (Ushiba)
 * Checking cable noise for PEM (T.Takana)
 * PEM: Vibration measurement at IXC (Yokozawa)
 * Measurement for PRs (Shoda)


=== Evening ===
 * Fiber noise cancellation (Enomoto)

=== Weekend ===
 * Fiber noise cancellation work at PSL on Saturday and Sunday(Enomoto, Sugimoto)
  * Changing optics for Yarm.
 * Venting again on Sunday morning (Ushiba)
  * Monitor for venting ITMY (Okutomi)
 * ETMX work on Saturday and Sunday(Fujii)
 

=== Monday Morning ===
 * SRs TF measurement, off load (Fabian)

=== Monday Aftenoon ===
 * SRs TF measurement, off load (Fabian)

=== Monday Evening ===
----

== Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM ==
Commissioning leader: Miyakawa (22nd-26th)

=== Afternoon ===
 * Fixing ITMY stuck (Okutomi)
 * ASC test on ITMX (Ushiba)
 * ETMX work (Fujii)
 * SR3 work for control loop IM yaw (Terrence)
 * Cabling for BIO this afternoon (Enomoto)
 * Xarm ALS hand over to IR using TR (Enomoto)
 * OMC characterization with control (Kokeyama, Darkhan)

=== Evening ===
 * Xarm ALS hand over to IR using TR (Enomoto)

=== Weekend ===

=== Morning ===
 * ITMY damping (Okutomi)
 * Type A work (Fujii)
 * ITMX damping (Ushiba)
 * Cryo cooler valve exchange (Kimura, Ushiba)
 * SR3 TF measurement (Fabian)
 * Automation for SR3 and SRM (Shoda)
 * Noise source by cable or something in the center room (Yokozawa)
 * Setting magnet meter at Y end (Yokozawa)

----

== Today's work plan: 2019/7/24 1PM - 2019/7/25 1PM ==
Commissioning leader: Miyakawa (22nd-26th)

=== Afternoon ===
 * Replacing LVDT driver on SR3(Fabian)
 * Single arm locking (Nakano)
 * Fix AC to stablize temeparute (Miyoki)
 * ITMY damping (Okutomi)
 * Maintenance for Ondotori (Yokozawa, T. Tanaka)
 * ALS model medication (Enomoto, Sugimoto)
 * MZ in PSL room for a hour (Guiguo)
 * OMC characterization with control (Kokeyama, Darkhan)

=== Evening ===
 * ALS hand over to IR using TR (Nakano, Enomoto)
 * DRFPMI lock (Nakano, Enomoto)

=== Weekend ===

=== Morning ===
 * ITMY damping (Okutomi)
 * Type A work (Fujii)
 * SR3 OSEM check (Fabian, Terrence)
 * Automation for Suspensions except for SR3 (Shoda)

----
== Standing issues ==
 * Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
 * Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
 * Y-arm lock
  * ETMY suspension control
  * ITMY damping
   * One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  *
 * DRMI lock stability
  * Model HOM-PHD signal distortion (Aso, Kokeyama)
  * Search for better Gouy phase in PRC
 * Initial alignment automation (Nakano)
 * IFO configuration Guardian (Kokeyama)
 * SDF for all the VIS (Shoda, Okutomi)
 * Type-A related
  * Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
  * United Guardian for all 4 suspensions (Okutomi)
  * Damping
  * Exchanging modified HPCD.
  * Type A: Feed forward technic to suppress extra motion (Nakano)
 * Type-B related
  * SR3 Yaw motion is too large (Fabian, Terrence)
 * Type-C related
  * OSEM characterization for OSTM (on going, Takahashi)
 * OMC
  * Check the OMC on the AS table
  * OMC characterization with control

 * Laser safety
  * Debug the laser safety guardian (Nakano)

 * IR QPD, centering on IR , green QPD at ETMY (Akutsu)

 * AS tube installation on 7/30-31 (Michimura)
 * Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
 * Fiber noise cancellation on Saturday (Enomoto, Sugimoto)

------
 

== Today's work plan: 2019/7/23 1PM - 2019/7/24 1PM ==
Commissioning leader: Miyakawa (22nd-26th)

=== Afternoon ===
 * PEM: 320.5Hz noise (Yokozawa)
 * Preparation for fiber noise cancellation (Enomoto, Sugimoto)
  * This turns on air filters.
 * OMC control (Kokeyama, Darkhan)
 * ALS hand over to IR(Stefan, Valera, Nakano)

=== Evening ===
 * ALS hand over to IR (Stefan, Valera, Nakano)
 * DRFPMI lock (Stefan, Valera, Nakano)

=== Weekend ===

=== Morning (Monday) ===
 * ITMY damping (Okutomi)
 * Type A work (Fujii)
 * SR3 OSEM check (Fabian)
  * DGS maintenance for prm or srm.
 * Adding BIO card to k1als0, k1ioo1.
 * Exchanging old type modified HPCD. (Ushiba, Takahashi)
 * ISS control servo (Yoshioka, Kokeyama)
----

== Today's work plan: 2019/7/22 1PM - 2019/7/23 1PM ==
Commissioning leader: Miyakawa (22nd-26th)

=== Afternoon ===
 * Exchanging HPCD(Fabian, Washimini)
  * check the range of new HPCD using oplev (Valera, Nakano).
 * ITMY damping (Okutomi)
 * ALS sweep to find IR resonance (MN, VF)
  * TEMP00 lock with dither(Nakano).

=== Evening ===
 * ALS sweep to find IR resonance (MN, VF)
 * DRMI lock (Stefan)

=== Weekend ===

=== Morning (Monday) ===
 * ITMY damping (Okutomi)
 * SR3 OSEM check (Fabian)
 * Type A: Feed forward technic to suppress extra motion (Nakano)
Line 27: Line 534:
----
Line 56: Line 564:
----

Archive of the Daily Commissioning Meeting at 1PM


Today's work plan: 2019/8/9 1PM - 2019/8/15 1PM

Afternoon

  • Hunting ITMY big morion (Lucia)
  • Type A work (Fujii, Lucia)
  • Work for fiber cancelation for replacing power supply to avoid magnetic field of small DC power supply (Enomoto, Sugimoto)
  • SR3 TF measurement (Fabian)
  • Restarting DAQ at 5pm (Yamamoto)
  • PEM: measure vibration noise of pump (Yokozawa, Kaihotsu)
  • PEM: measure fiber noise for ALS (Washimi)
  • CAL: AOM will be tested from control room for Y end (Inoue)
  • ISS work outside PSL (Yoshioka, Kuromiya, Nakano)
  • Covering for TMS at ETMX (Akutsu)

Evening

  • Finesse measurement (Nakano)
  • IFO works with Yarm for FPMI (Nakano)
  • Work for fiber cancelation (Enomoto, Sugimoto)
  • Leave IFO locked from night to morning (Nakano)

Weekend

  • IFO works with Yarm (Nakano)
  • Work for fiber cancelation (Enomoto, Sugimoto)

Morning


Today's work plan: 2019/8/8 1PM - 2019/8/9 1PM

Afternoon

  • Leak check at ITMY (Kimura)
  • Work for fiber cancelation (Enomoto, Sugimoto)
  • Measure TF of ITMY for top part by making health check list (Liucia)
  • Starting EY cry cooler (Kimura)
  • Put cover on TMSX at X end (Akutsu)
  • OSTM work (Takahashi)
  • CAL: Replacing AOM at ETMY, tuning camera at ETMY (Inoue)
  • SR3 TF measurement (Fabian)

Evening

  • Work for fiber cancelation (Enomoto, Sugimoto, Akutsu)
  • Some IFO work with Yarm (Nakano)
  • Leave IFO locked (Nakano)

Weekend

Morning

  • Stop ETMX cryo cooler (Kimura)
  • SR3 TF measurement (Fabian)
  • X fiber noise for temp. control (Enomoto, Sugimoto)
  • Type A work (Fujii, Lucia)
  • ISS servo in the PLS morning (Yoshioka)


Today's work plan: 2019/8/7 1PM - 2019/8/8 1PM

Afternoon

  • Lock fiber cancelation, entering PSL and turning off filters (Enomoto, Sugimoto)
  • ISS work outside of PSL (Yoshioka, Nakano)
  • SR3 noise investigation (Fabian)
  • Measure TF of ITMY for top part by making health check list (Liucia)
  • OSTM work (Takahashi)
  • Exchanging IX oplev source (Akutsu)

Evening

  • One arm WFS test with X arm(Nakano)
  • Leave IFO locked (Nakano)

Weekend

Morning

  • X fiber noise control or temperate control for Y (Enomoto, Sugimoto)
  • SR2, 3 noise investigation (Fabian)
  • OSTM work (Takahashi)
  • Type A work (Fujii, Lucia)


Today's work plan: 2019/8/6 1PM - 2019/8/7 1PM

Afternoon

  • Opening GV for ITMX (VAC)
  • ITMX oplev work before Finesse measurement (Yamada)
  • Finesse measurement for Xarm (Nakano)
  • Measure TF of ITMY for top and cryopayload by making health check list (Okutomi, Yamada)
  • OSTM work (Takahashi)
  • WFS centering at REFL (Nakano)
  • HDD installation for CAL PC (Darkhan)
  • Exchanging PC for VAC mon (Yokozawa)

Evening

  • One arm WFS test with X arm(Nakano)
  • Leave IFO locked (Nakano)

Weekend

Morning

  • Exchanging k1dc0 in early morning 8am (Yamamoto, Oshino)
  • Fiber cancelation work (Enomoto, Sugimoto)
  • ISS work in the PSL (Yoshioka)
  • SR2, 3 noise investigation (Fabian)
  • OSTM work (Takahashi)
  • Type A work (Fujii, Lucia)


Standing issues 2019/8/5

  • Sensitivity monitor for various DoF (CAL)
  • PEM - measured data sharing (Washimi, Yokozawa)
  • How to control the PSL temperature when people enters the room (Miyoki)
  • We need IFO commissioning strategy!!!
  • One arm WFS test
  • DRMI lock stability
    • 3f transition
    • Search for better Gouy phase in PRC
  • PRFRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • Arm: transition
    • Y-arm lock
  • Try ALS mass lock with FFUs and ACs turned off
  • Type-A related
    • Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Exchanging modified HPCD.
    • Type A: Feed forward technic to suppress extra motion (Nakano)

Meeting archive


Today's work plan: 2019/8/5 1PM - 2019/8/6 1PM

Afternoon

  • Damping monitor (Okutomi, Lucia)
  • Finesse measurement for Xarm. (Nakano)
  • Damping work for Type A. (Fujii)
  • SR2, 3 noise investigation (Fabian)
  • Entering cleaning area for taking pictures (with Yokozawa)
  • Cabling ALS fiber noise cancellation (Enomonoto, Miyoki)
  • OSTM work for OSEM inve(Takahashi)

Evening

  • One arm WFS test (Nakano)

Weekend

Morning

  • Fix vacuum monitor (Yokozawa)
  • Increasing ITMX temperature (CRY)
  • Entering cleaning area for taking pictures (with Kokeyama)
  • SR2, 3 noise investigation (Fabian)
  • Installation circuit to ITMY, and control test (Yamada)
  • OSTM work (Takahashi)
  • Fixing k1IOO1 (Yamamoto)
  • IXV work (Fujii)


Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM

Afternoon

  • GV opened last night
  • ITMY release ongoing (CRY, VIS)
  • After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
  • Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
  • Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
  • Type-A common guardian
  • Oplev swap for IMMT2
  • Oplev swap for PR2 if possible with IFO

Evening

  • Finesse measurement
  • Arm transition method commissioning

Morning

  • Continued SRs study (Fabian)
  • IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)

We want a sensitivity monitor!

We want to plan Feedforward on typeA!

We want to decide the Commissioning strategy!

Note

  • IY chamber will be closed on Saturday


Today's work plan: 2019/8/2 1PM - 2019/8/5 1PM

Afternoon

  • ITMY problem investigation (CRY&VIS)

  • Finesse measurement (Nakano)
  • X-arm transition (Nakano)
  • ISS (Yoshioka)
  • ITMX Type-A control (VGAS oscillation) (Lucia)
  • PEM measurements around IFO REFL (Yokozawa)
  • ALS fiber noise cancellation (Enomonoto)

Weekend

  • Fiber noise cancellation
    • Turn off FFU, ACs

8/5 Morning

  • ITMY pumping (VIS, CRY)
  • SR2, 3 noise investigation (Fabian)
  • DGS maintenance (Yamamomot, Oshio, Miyakawa)
    • dc0 replacement
    • Add BIO to k1ioo1
  • Installation of circuit to ALS (Enomoto)


Today's work plan: 2019/8/1 1PM - 2019/8/2 1PM

Afternoon

  • GV opened last night
  • ITMY release ongoing (CRY, VIS)
  • After releasing, ITMY alignment using MICH (Nakano, CRY, VIS)
  • Fabian will investigate the difference between FLOAT and ALIGNED (Fabian)
  • Finesse re-measurement (Nakano) - We might want to warm up IY. To be discussed. Maybe if 70-80K doesn't recover the finesse.
  • Type-A common guardian
  • Oplev swap for IMMT2
  • Oplev swap for PR2 if possible with IFO

Evening

  • Finesse measurement
  • Arm transition method commissioning

Morning

  • Continued SRs study (Fabian)
  • IY final checks (earthquake stops etc) and cleaning (Aso, Ushiba)

We want a sensitivity monitor!

We want to plan Feedforward on typeA!

We want to decide the Commissioning strategy!

Note

  • IY chamber will be closed on Saturday


Today's work plan: 2019/7/31 1PM - 2019/8/1 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • ITMY: BF work. (Okutomi, Sato, Fujii)
  • ITMY: H1 actuator investigation. (Ushiba, Yamada)
  • PEM: Reporting Temperature. (Yokozawa)
  • VAC, MIF: Opning GV, alingment. (Saito, Nakano, Michimura, Akutsu)
  • ASO: Small works at ETMX (Akutsu)
  • Replacing light source for IMMT2. (Akutsu)
  • Type B: Back to aligned mode. (Fabian)
  • DET: replacing OS of DET computer for offline analysis. (T.Yamamoto)
  • CAL: Xend Tcam will be touched. (Inoue)

Evening

  • IFO some work. (Nakano, Michimura, Akutsu)
  • VIS work can be done for Y arm work since Y arm is not available for a while. (Fujii, Okutomi)

Weekend

Morning

  • Releasing ITMY suspension. (Ushiba)
  • PSL work for grounding problem. (Nakano)
  • Maintenance for Ondotori at X-end (T.Yamamoto)


Today's work plan: 2019/7/30 1PM - 2019/7/31 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
  • Check H1 actuator. (Ushiba, Tomaru, Yamada)
  • ALS: Tuning returning beam at center area, and in PSL room shortly. (Enomoto, Sugimoto)
  • Connecting tube on the AS table. (Michimura)
  • ISS: work for servo in the PSL for 30min. (Yoshioka, Nakano)
  • AOS: Some small works in the center room for oplev. (Akutsu)
  • PEM: test a new sensor at IY0 rack. (Yokozawa, Washimi)
  • BS: measurement of noise. (Fabian)

Evening

  • IFO some work. (Nakano, Michimura, Akutsu)

Weekend

Morning

  • DGS maintenance for exchanging k1dc0, adding BIO cards to k1ioo1 for ALS control (Yamamoto, Oshino)
    • VIS should go safe mode. (Fabian)
    • DC power source will be exchanged at ALS0 and ALS1 rack. (Kamiizumi)
  • Fix ITYM F0 motor and to check BF. (Okutomi, Sato, Fujii)
  • Connecting tube on the AS table. (Michimura)
  • AOS: Some small works at Y end for oplev. (Akutsu)
  • PEM: work around IYC chamber. (Yokozawa, Washimi)


Today's work plan: 2019/7/26 1PM - 2019/7/30 1PM

Commissioning leader: Miyakawa (July 29-30), Aso (August 1-3)

Afternoon

  • Monitor for venting ITMY (Okutomi)
    • Updating RT model for Type A, except for ITMY (Okutomi)
  • ASC test on ITMX (Ushiba)
  • ETMX work (Fujii)
  • SR3 work for control loop IM yaw (Fabian)
  • OMC characterization with control (Kokeyama, Somiya)
  • Fiber noise cancellation at control room(Enomoto, Sugimoto)
  • ISS put wind shield outside PSL (Yoshioka, Kukromiya)
  • Pick up Moku:Lab (Guiguo)

  • Stop venting around the evening (Ushiba)
  • Checking cable noise for PEM (T.Takana)
  • PEM: Vibration measurement at IXC (Yokozawa)
  • Measurement for PRs (Shoda)

Evening

  • Fiber noise cancellation (Enomoto)

Weekend

  • Fiber noise cancellation work at PSL on Saturday and Sunday(Enomoto, Sugimoto)
    • Changing optics for Yarm.
  • Venting again on Sunday morning (Ushiba)
    • Monitor for venting ITMY (Okutomi)
  • ETMX work on Saturday and Sunday(Fujii)

Monday Morning

  • SRs TF measurement, off load (Fabian)

Monday Aftenoon

  • SRs TF measurement, off load (Fabian)

Monday Evening


Today's work plan: 2019/7/25 1PM - 2019/7/26 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Fixing ITMY stuck (Okutomi)
  • ASC test on ITMX (Ushiba)
  • ETMX work (Fujii)
  • SR3 work for control loop IM yaw (Terrence)
  • Cabling for BIO this afternoon (Enomoto)
  • Xarm ALS hand over to IR using TR (Enomoto)
  • OMC characterization with control (Kokeyama, Darkhan)

Evening

  • Xarm ALS hand over to IR using TR (Enomoto)

Weekend

Morning

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • ITMX damping (Ushiba)
  • Cryo cooler valve exchange (Kimura, Ushiba)
  • SR3 TF measurement (Fabian)
  • Automation for SR3 and SRM (Shoda)
  • Noise source by cable or something in the center room (Yokozawa)
  • Setting magnet meter at Y end (Yokozawa)


Today's work plan: 2019/7/24 1PM - 2019/7/25 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Replacing LVDT driver on SR3(Fabian)
  • Single arm locking (Nakano)
  • Fix AC to stablize temeparute (Miyoki)
  • ITMY damping (Okutomi)
  • Maintenance for Ondotori (Yokozawa, T. Tanaka)
  • ALS model medication (Enomoto, Sugimoto)
  • MZ in PSL room for a hour (Guiguo)
  • OMC characterization with control (Kokeyama, Darkhan)

Evening

  • ALS hand over to IR using TR (Nakano, Enomoto)
  • DRFPMI lock (Nakano, Enomoto)

Weekend

Morning

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • SR3 OSEM check (Fabian, Terrence)
  • Automation for Suspensions except for SR3 (Shoda)


Standing issues

  • Try FPPRMI: with stable 3f signals and ALS extra range, FPPRMI may fix the glitches?
  • Fast shut off feature on type-A after lockloss not to ring (real time model change, Stefan)
  • Y-arm lock
    • ETMY suspension control
    • ITMY damping
      • One IM magnet is broken. Need a different strategy. Use MN ? (Yamada, Okutomi)
  • DRMI lock stability
    • Model HOM-PHD signal distortion (Aso, Kokeyama)
    • Search for better Gouy phase in PRC
  • Initial alignment automation (Nakano)
  • IFO configuration Guardian (Kokeyama)
  • SDF for all the VIS (Shoda, Okutomi)
  • Type-A related
    • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
    • United Guardian for all 4 suspensions (Okutomi)
    • Damping
    • Exchanging modified HPCD.
    • Type A: Feed forward technic to suppress extra motion (Nakano)
  • Type-B related
    • SR3 Yaw motion is too large (Fabian, Terrence)
  • Type-C related
    • OSEM characterization for OSTM (on going, Takahashi)
  • OMC
    • Check the OMC on the AS table
    • OMC characterization with control
  • Laser safety
    • Debug the laser safety guardian (Nakano)
  • IR QPD, centering on IR , green QPD at ETMY (Akutsu)
  • AS tube installation on 7/30-31 (Michimura)
  • Valve unit exchange for ITMX on 7/26 for 1-2 hours (Kimura)
  • Fiber noise cancellation on Saturday (Enomoto, Sugimoto)


Today's work plan: 2019/7/23 1PM - 2019/7/24 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • PEM: 320.5Hz noise (Yokozawa)
  • Preparation for fiber noise cancellation (Enomoto, Sugimoto)
    • This turns on air filters.
  • OMC control (Kokeyama, Darkhan)
  • ALS hand over to IR(Stefan, Valera, Nakano)

Evening

  • ALS hand over to IR (Stefan, Valera, Nakano)
  • DRFPMI lock (Stefan, Valera, Nakano)

Weekend

Morning (Monday)

  • ITMY damping (Okutomi)
  • Type A work (Fujii)
  • SR3 OSEM check (Fabian)
    • DGS maintenance for prm or srm.
  • Adding BIO card to k1als0, k1ioo1.
  • Exchanging old type modified HPCD. (Ushiba, Takahashi)
  • ISS control servo (Yoshioka, Kokeyama)


Today's work plan: 2019/7/22 1PM - 2019/7/23 1PM

Commissioning leader: Miyakawa (22nd-26th)

Afternoon

  • Exchanging HPCD(Fabian, Washimini)
    • check the range of new HPCD using oplev (Valera, Nakano).
  • ITMY damping (Okutomi)
  • ALS sweep to find IR resonance (MN, VF)
    • TEMP00 lock with dither(Nakano).

Evening

  • ALS sweep to find IR resonance (MN, VF)
  • DRMI lock (Stefan)

Weekend

Morning (Monday)

  • ITMY damping (Okutomi)
  • SR3 OSEM check (Fabian)
  • Type A: Feed forward technic to suppress extra motion (Nakano)


Today's work plan: 2019/7/19 1PM - 2019/7/22 1PM

Commissioning leader: Aso (19th), Miyakawa (22nd)

Afternoon

  • ALS sweep to find IR resonance (MN, VF)
  • Start X-End cryocooler (Yamada, TakahashiM)
  • Implement BF stage control on ALIGNED state on type-A guardian (Kokeyama)
  • ISS servo setup and OLTF measurement (Yoshioka, Kuromiya, Yamamoto)
  • Serial number check of OpLev SLDs (Yamada)

Evening

  • ALS sweep to find IR resonance (MN, VF)

Weekend

  • IFO configuration guardian (Kokeyama, Saturday)
  • Modification of the IMC servo (Enomoto, Sunday)
  • Transition to IR (Nakano, Valera, Sat & Sun)

  • TF measurement of Type-A (Yamada, Saturday morning)
  • ITM actuator efficiency measurement (Sun morning ?)

Morning (Monday)

  • SR3 OSEM check (Fabian)


Today's work plan: 2019/7/17 1PM - 2019/7/18 1PM

Commissioning leader: Aso (July 17th-19th)

Afternoon

  • ETMY HP coil driver check (Takahashi, Yamada)
    • Watchdog, Output resistance, Cable resistance, Take a picture of the PCB
  • Check the maximum current acceptable by the in-vac cable.
    • Calculate theoretical limit (Ushiba)
  • AS alignment (Kokeyama et al)
  • SR3 OSEM check (Fabian, Terrence)
  • Y-arm mass lock trial (SB, EY, MN, et al)
  • ISS work (Yoshioka, Nakano)

Evening

  • Y-arm mass lock trial (SB, EY, MN, et al)
  • Type-A guardian work on ETMX (Kokeyama)
  • DRMI investigation ? (SB, EY, MN, et al)
  • Found Y end coil needed more range, more drive for MN (dominate 10Hz sensing noise limited, cross over)

Note

  • DC feedback works perfect
  • Tcam alignment system is done (see from camera screen)
  • ALIGNED guardian on ETMX (test phase)

Morning

  • HP coil driver modification ? (Yamada, Fabian, Terrence)


KAGRA/Commissioning/DailyMeetingArchive (last edited 2019-11-19 09:15:27 by OsamuMiyakawa)