2017/1/11(Thrs.) * Remote participants by educe: None * Report of work (*:responsible person) * Work plan (*:responsible person) * Alignment: *Izumi * Oplev, Re-alignment * Check of PLC at Yend for connection to measurement tools: Aso * Marionet Oplev: Akutsu * Laser hazard area * Behind of BS and SR line and Yend 1F * Weekly * Week of 1/8 * 1/11, 12: Re-alignment for IFO. * 1/13, 14: Damping for ETMY. * Week of 1/15 * IOO works. * 1/19: Pump down. * Week of 1/22 * 1/24,25 leak check. * Week of 1/29 * 1/29 Cooling start * Issues