2017/2/5(Mon.) * Remote participants by eZuce: Takahashi, Aso * Report of work (*:responsible person) * Vibration Isolation, * Restarted the BS realtime model. * Alignment: Izumi, Okutomi * ETMY transfer function has a different shape from what was measured before in the air. It means that ETMY might be touching somewhere. * For vertical, below BF transfer function seems to be OK. * Yaw might be rotating too much. * After 1/17, ETMY started showing something strange. Stiffness changed gradually, but Q did not change much. * Work plan (*:responsible person) * Alignment: *Izumi, Okutomi * We will rotate IP yaw to release somewhere touching. This work takes 1day at least. * Detchar for spectrum of suspension is necessary as soon as possible. * Vacuum * Gate valve will be closed today. * Needs 2days for evacuation. If once evacuated, cooling will be late ~2weeks. * Type B * SR assembly continues. * Laser hazard: PSL. At some in this evening, it will be the are over the SR line for double-checking the IMC alignment. Kokeyama is responsible for it. * Weekly * Week of 2/5 * Finding causes of ETMY trouble. * Evacuation might be needed if ETMY is touching somewhere. * Cooling also will be delayed for 2weeks or so. * Issues * The ETMY mirror showed a strange scattering pattern.