2017/2/9(Fri.) * Remote participants by eZuce: None * Report of work (*:responsible person) * Alignment and Vibration Isolation: *Miyakawa * Drift by cooling is small. * Cooling: *Kimura, Suzuki, Yokozawa, Aso, Miyakawa, Miyamoto * One of the cooled was stopped due to the leak of water. This will be fixed in the next week. It does not affect the schedule of cooling. (Kimura) * PLC values are fixed. Power cable on the wall once accidentally might be unplugged and plugged, then PC was not turned on. (Aso) * Some of the temperature channels have been fixed. (Miyakawa, Miyamoto, Yokozawa) * Work plan (*:responsible person) * Laser hazard: PSL room in the morning. IMM in the afternoon. * Weekly * Week of 2/5 * 2/7 Cooling. * Issues