* Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs. * Watch dog bug report: *Mark * Or stage was implemented instead of And stage at the watch dog part. |
|
Line 18: | Line 14: |
* CAL: *Haino * To check the safety of laser. |
* Servers will be turned on. Timing difference by power outage, we need reboot the timing system and all the RT PCs. |
Line 22: | Line 19: |
* Oplev will be centered and beam will be checked again. * PR2 will be lowered by ~3mm. |
* Damping tuning |
2017/2/19(Mon.)
- Remote participants by eZuce: None
- Recovery from the power outage in the morning.
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto
- Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.
- Alignment and ETMY: *Izumi, Enomomoto
Glitch is still there but even if measurement with no glitch time has still no coherence.
- PR RT models will be modified for Watch dog bug or something.
- Work plan (*:responsible person)
- Servers will be turned on. Timing difference by power outage, we need reboot the timing system and all the RT PCs.
- ETMY: Enomomoto, Izumi
- Damping tuning
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- 2/19 Recovering for power down.
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues