Differences between revisions 1 and 3 (spanning 2 versions)
Revision 1 as of 2018-02-19 09:10:20
Size: 1215
Comment:
Revision 3 as of 2018-02-20 08:56:04
Size: 995
Comment:
Deletions are marked like this. Additions are marked like this.
Line 12: Line 12:
 * Servers are turned on. Timing changed by power outage, we need reboot timing system and all the RT PCs.

 * Watch dog bug report: *Mark
  * Or stage was implemented instead of And stage at the watch dog part.
Line 18: Line 14:
  * CAL: *Haino
   * To check the safety of laser.

  * Servers will be turned on. Timing difference by power outage, we need reboot the timing system and all the RT PCs.
Line 22: Line 19:
   * Oplev will be centered and beam will be checked again.
   * PR2 will be lowered by ~3mm.
   * Damping tuning

2017/2/19(Mon.)

  • Remote participants by eZuce: None
    • Recovery from the power outage in the morning.
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Izumi, Enomomoto
      • Measurement of TF of ETMY for all the DOFs. TF of Marionette was measured again and the sensing matrixes were tuned.

Glitch is still there but even if measurement with no glitch time has still no coherence.

  • PR RT models will be modified for Watch dog bug or something.
  • Work plan (*:responsible person)
    • Servers will be turned on. Timing difference by power outage, we need reboot the timing system and all the RT PCs.
    • ETMY: Enomomoto, Izumi
      • Damping tuning
  • Laser hazard: Upstream SR2-3 line.
  • Weekly
    • Week of 2/19
      • 2/19 Recovering for power down.
      • ETMY tuninng.
    • Week of 2/26
      • Beam alignment to REFL port.
    • week of 3/5
      • IYC door will be closed.
    • week of 3/12
      • Connecting ducts at corner.
  • Issues

KAGRA/Commissioning/DailyWork/2018-02-19 (last edited 2018-02-20 09:07:13 by OsamuMiyakawa)