Size: 1191
Comment:
|
← Revision 5 as of 2018-02-22 09:07:59 ⇥
Size: 1215
Comment:
|
Deletions are marked like this. | Additions are marked like this. |
Line 7: | Line 7: |
* We moved IP position to find where it does not touch anywhere, but TF showed resonant frequency was higher. We think heat link make some torque. | * IP was moved to find where it does not touch anywhere, but TF showed resonant frequency was higher than before. We think heat link make some non ignorable torque. |
Line 9: | Line 9: |
* BS: Kozu * Finished measurement the TF of TM and IM coupling. |
* BS: Kozu * Measurement the TF of TM and IM coupling was done. |
Line 12: | Line 12: |
* Team: *Inoue * Team at Yend was broken. Taking too many pictures was one of the reasons. |
* Tcam: *Inoue * Tcam at Yend was broken. Taking too many pictures was one of the reasons. |
Line 15: | Line 15: |
* ISS: Koseyama, and Toyama Univ. * Error signal is limited by shot noise, but outlook noise is still higher. |
* ISS: Koseyama, and Toyama Univ. * Error signal is limited by shot noise, but outlook noise is still higher. |
Line 23: | Line 23: |
* Team: | * Tcam: |
2017/2/21(Wed.)
- Remote participants by eZuce: None
- Report of work (*:responsible person)
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- IP was moved to find where it does not touch anywhere, but TF showed resonant frequency was higher than before. We think heat link make some non ignorable torque.
- BS: Kozu
- Measurement the TF of TM and IM coupling was done.
- Tcam: *Inoue
- Tcam at Yend was broken. Taking too many pictures was one of the reasons.
- ISS: Koseyama, and Toyama Univ.
- Error signal is limited by shot noise, but outlook noise is still higher.
- Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora
- Work plan (*:responsible person)
- ETMY: Enomomoto, Izumi
- Diagonalizing matrix to close loop of marionette.
- Tcam:
- Debugging NIKON camera.
- IYA monitor: Yokozawa
- IYA monitor will start.
- ISS: Koseyama, and Toyama Univ.
- Investigating noise.
- ETMY: Enomomoto, Izumi
- Laser hazard: Upstream SR2-3 line.
- Weekly
- Week of 2/19
- ETMY tuninng.
- Week of 2/26
- Beam alignment to REFL port.
- week of 3/5
- IYC door will be closed.
- week of 3/12
- Connecting ducts at corner.
- Week of 2/19
- Issues
- Heat link make some torque.