2017/2/22(Thur.) * Remote participants by eZuce: Miyoki * Report of work (*:responsible person) * Alignment and ETMY: *Izumi, Enomomoto, Ushiba, Elenora * Diagonalizing input matrix. Electronics was something wrong, like oscillation. * Work plan (*:responsible person) * ETMY: Enomomoto, Izumi * Diagonalizing matrix to close loop of marionette. * ISS: Koseyama, Kitazawa * Making RT models. * Laser hazard: AM: PSL, PM: Upstream SR2-3 line. * Weekly * Week of 2/19 * ETMY tuninng. * Week of 2/26 * Beam alignment to REFL port. * Height change for PRs * week of 3/5 * IYC door will be closed. * week of 3/12 * Exchanging items and cleaning inside the PR2 chamber * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * Issues