Differences between revisions 2 and 3
Revision 2 as of 2018-02-28 08:57:48
Size: 1532
Comment:
Revision 3 as of 2018-02-28 09:12:11
Size: 1536
Comment:
Deletions are marked like this. Additions are marked like this.
Line 21: Line 21:
 * Camera: Yokozawa
  * fine tuning and safety.
  * Camera: Yokozawa
  * fine tuning and safety.
Line 24: Line 24:
 * Height change of PRs:
  * It will be planed tomorrow. Preparation is almost done.
  * Height change of PRs:
  * It will be planed tomorrow. Preparation is almost done.

2017/2/27(Tue.)

  • Remote participants by eZuce: Izumi
  • Report of work (*:responsible person)
    • Alignment and ETMY: *Enomoto, Ushiba, Yamamoto
      • Beam was lost at the ETMX and ETMY. We will check actual beam inside the chambers at the center area.
      • Sampling model of RT model was changed from 16kHz to 2kHz and glitches disappeared!
    • IOO: kokeyama
      • IO chassis has been replaced but it did not work due to PC's problem. The PC was replaced and seemed to be OK. but IRIG-B showed 9999xx still.
    • CRY: mirror temperature ~110K.
      • The satellite amplifier has an oscillation for photo sensors at low temperature. Satellite amplifiers which will be used for photo sensors at low temperature should be modified.
  • Work plan (*:responsible person)
    • ETMY: Enomomoto, Ushiba
      • Original REFL port will be tested to pick up Mich signal.
    • Camera: Yokozawa
      • fine tuning and safety.
    • Height change of PRs:
      • It will be planed tomorrow. Preparation is almost done.
  • Laser hazard: AM: PSL, PM: Upstream SR2-3 line, and Y-end.
  • Weekly
    • Week of 2/26
      • ETMY tuninng.
      • Beam alignment to REFL port.
      • 2/28: Height change for PRs
    • week of 3/5
      • IYC door will be closed.
      • Exchanging items and cleaning inside the PR2 chamber
    • week of 3/12
      • TMS installation at ETMY.
      • Connecting ducts at the corner area.
    • week of 3/19
      • Vacuum test at at the corner area.
      • TMS alignment using green light at ETMY.
  • Issues

KAGRA/Commissioning/DailyWork/2018-02-27 (last edited 2018-02-28 09:12:44 by OsamuMiyakawa)