2017/3/8(Fri.) * Remote participants by eZuce: Miyoki ==== Report of work (*:responsible person) ==== * Alignment: *Enomoto, Michimura * Tuning of ETMY damping. * PD of transmitted light of ETMY was implemented. * Oplev of are centered. * Yaw of 0.2Hz of ETMY is still moving. RMS is limited by this ~10urad. * CRY: mirror temperature started increasing because of turning one of the cryo pump off. * Tcam: *Inoue, Cory, Binhua * phi800 door of IX will be closed Monday, IY will be closed Tuesday or Wednesday. ==== Work plan (*:responsible person) ==== ==== Laser hazard ==== * [AM] IR: PSL, Green: PR2. * [PM] IR: PSL, Green: PR2. ==== Weekly ==== * week of 3/5 * 3/8 IYC door will be closed. * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. * Issues * Connection of PD signal to DAQ should be implemented this week or next week. * GigE camera should be placed at the REFL port eventually.