2017/3/15(Thur.) * Remote participants by eZuce: None ==== Report of work (*:responsible person) ==== * Alignment, ETMY: *Enomoto, Miyo, Miyamoto, Izumi * Tuning of ETMY damping is still going on. * Beam alignment to both end and REFL port was confirmed the last night. * Beam is now being drifted to down slowly at PSL by ~100urad. * One of the DAC channel of IMMT puts half voltage. We changed the channel position in the software. * When the bottom screws was tightened, oplev showed the shift of IMMT1 at least. * BS: Top of the BS chamber was tightened but no big shift was not found. * AOS: IYC and IYA started pumping down. * ETMY: *Enomoto * BF of tower of ETMY matrix was messed up. Polarity was changed by phase shift or something. * CRY: Mirror reached at 18K. ==== Work plan (*:responsible person) ==== * Alignment: Enomonoto, Izumi * IMMT coil driver will be checked. * REFL camera has been placed and will be setup today. * VAC: Uchiyama * Duct connection. * Camera: Yokozawa * Both door will be closed today. Pump down will be start today. * AOS: IYC will be closed and start pump-down. ==== Laser hazard ==== * [AM] IR: PSL, Green: off. * [PM] IR: PSL, Green: off. * [night] IR: all, Green: off ==== Weekly ==== * week of 3/12 * 3/14: meeting for pump-down check * TMS installation at ETMY. * Connecting ducts at the corner area. * week of 3/19 * Vacuum test at at the corner area. * TMS alignment using green light at ETMY. * Beam alignment to REFL port. * Issues * Connection of PD signal to DAQ should be implemented this week or next week.