2017/3/19(Mon.) * Remote participants by eZuce: Kimura ==== Report of work (*:responsible person) ==== * VAC: *Uchiyama, Kimura, Suzuki * 4-5 turbo pumps started. * Currently vacuum level is ~1e-4Pa. * Some leaks were found. Fixing leaks around BS can be fixed easily, but fixing leaks around MC is not so easy. In any case, we need vent again. * New control boxes for gate valve test were done. * Currently they work at local place, but they will be controlled remotely in the future. * Vacuum chamber of Y-direction of BS is inclined to the gate valve direction by factor of 2mm. * PR2 assembly frames will be removed soon. * Power cable was connected to the ground at the power panel and made a short to the ground. ==== Work plan (*:responsible person) ==== * Alignment, ETMY: *Izumi * All alignment after pump down will be checked. * PR3 yaw had some drift during pump-down. * Cal: * Calibration test using MC is planned on Wednesday. * VAC: Kimura, Sawada * Door will be closed at 3/23. * EX PD will be removed simonteninaously.: *Yokozawa ==== Laser hazard ==== * [AM] IR: all, Green: off. * [PM] IR: all, Green: off. * [night] IR: all, Green: off ==== Weekly ==== * week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Issues