2017/3/20(Tue.) * Remote participants by eZuce: None ==== Report of work (*:responsible person) ==== * VAC: *Uchiyama, Kimura, Suzuki * PR2 assembly frames will be removed soon. * Alignment: *Izumi * All alignment to REFL after pump down was verified. * Only ETMY was off position by ~100urad. * ETMY: *Miyamoto * Diagonal of sensors. Still going on. * BS: Eleonora, Izumi * Coil balance is going on. * IMC: * "sleep" commands were removed from Guardian. * Cal: Yokozawa * We checked all the IMC TFs. ==== Work plan (*:responsible person) ==== * Alignment, ETMY: *Izumi * Cal: Yokozawa * Injection will be tested soon. ==== Laser hazard ==== * [AM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [PM] IR: SR2-3 line, Yend 1F. Green: Yend 1F. * [night] IR: SR2-3 line, Yend 1F. Green: Yend 1F. ==== Weekly ==== * week of 3/19 * TMS alignment using green light at ETMY. * 3/21: Calibration test using MC. * 3/23: door between EXA and EXC will be removed. * EX PD will be removed at the same time.: *Yokozawa * week of 3/26 * Rough alignment of ETMX will be planed using IR. * 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area. * Issues