 * Camera: Yokozawa, Yamamoto, Miyamoto
  * X end camera will be recovered.
  * IYC cooling started.

2017/3/26(Mon.)

  • Remote participants by eZuce: Shoda

Report of work (*:responsible person)

  • ETMY: *Miyamoto
    • Mirror motion has been suppressed to ~2urad. Requirement is 1urad, pretty close!
  • BS: *Eleonora, Yamamoto
    • DAQ had trouble. Channel number is assigned to wrong channel, that was because RT model was built and installed but not restarted, and DAQ was restarted independently.
  • Camera: *Inoue
    • X end camera was recovered, needs PC tuning.

Work plan (*:responsible person)

  • BS: *Enomoto
    • Once oplev servo servo was engaged, yaw oscillation started. It will be investigated this week.
  • AOS: *Akutsu, Yokogawa
    • BRT alignment is still going on.
    • Oplev work at EXC. It will be available early this week.

Laser hazard

  • [AM]
    • IR: PSL
    • Green: none
  • [PM]
    • IR: PSL
    • Green: none
  • [night]
    • IR: PSL
    • Green: none

Weekly

  • week of 3/26
    • Connection of cable at ETMX and starting control.
    • Rough alignment of ETMX using IR.
      • EX PD will be removed.: *Yokozawa
    • 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
  • week of 4/2
    • ETMY damping.
    • Rough alignment of ETMX using IR, and control MICH if can.
  • week of 4/9
  • Issues