2017/3/27(Tue.)
- Remote participants by eZuce: Yokozawa
Report of work (*:responsible person)
- Cry and Type A at ETMX: *Takahashi, Ishizaki, Sato, Okutomi + CRY
- All are free except for Pre-isolator.
- Cable connections seemed to be fine.
- First contact will be removed.
- Oplev at ETMX: Akutsu
- Preparation is almost done.
- BS: *Enomoto
- Oplev servo servo oscillation was fixed by fixing channel assignment on digital system by restarting RT model.
Work plan (*:responsible person)
- Camera: *Inoue, Yokozawa
- ETMX PD will be removed.
- GigE camera will be removed today and placed next week.
- Oplev at ETMX: *Akutsu, Simon
- Once first contact is removed, opelev will be aligned.
- BRT: *Akutsu, Yokogawa, Sugimoto, Nagano, Yamamoto
- Alignment
Laser hazard
- [AM]
- IR: PSL
- Green: PR2
- [PM]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
- [night]
- IR: SR2-3 line, Xend 1F, Yend 1F
- Green: PR2, Xend 1F
Weekly
- week of 3/26
- 3/26 Pcal will start, and all the 1st floor of Y-end will be laser hazard area.
- Connection of cable at ETMX and starting control.
- Rough alignment of ETMX using IR.
- 3/27 EX PD will be removed.: *Yokozawa
- week of 4/2
- ETMY damping.
- Rough alignment of ETMX using IR, and control MICH if can.
- week of 4/9
- Issues