=== 2018/4/12(Thur.) === * Remote participants by eZuce: None ==== Report of work (*:responsible person) ==== * IFO: Enomoto, Nagano, Nagano * 5 front gate valve opened and beam was verified at the Y end baffle PD. * Beam shift was only ~10urad when the gate valve opened. * One of the monitor of gate valve did not work. * Final check at X end was done. * Coil driver for Marionette was changed from low to high. * Damping of ETMX will be tested with HPCD. ==== Work plan (*:responsible person) ==== * IFO: damping work or others. * VAC: closing ETMX door. * Pumping starts tomorrow morning. ==== Laser hazard ==== * [AM] * IR: PSL, Yend 1F * Green: off * [PM] * IR: PSL, Yend 1F * Green: off * [night] * IR: Upstream SR2-3 line, Yend 1F * Green: off ==== Weekly ==== * week of 4/9 * 4/11 12:30 at fan hut: Meeting before pump down 2 * Closing EXC * Some controls for Michelson * 4/13 morning: Pump down starts. * week of 4/16 * Michelson control * Leak check * week of 4/23 * Operation ==== Issues ====