* ETMY was improved a bit by Nakano. Now ~3urad.
  * ETMY damping was improved a bit by Nakano. Now ~3urad.

2018/4/13(Fri.)

* Remote participants by eZuce: Miyoki

Report of work (*:responsible person)

  • IFO: *Enomoto, Nakano, Nagano, Ohashi, Furuta, Yokozawa
    • Last night, the beam from ETMX was lost caused by probably a shit at oplev. Installing a view port might introduce the shift on oplev yaw.
    • Centering of oplev was done this morning
    • Alignment was tuned IMC from 0.3/1.0->0.7/1.0

    • ETMY damping was improved a bit by Nakano. Now ~3urad.
  • VAC: *Kimura
    • View port for oplev at ETMX was attached yesterday's afternoon.
    • All the preparation was done and the door of EXC was closed.

Work plan (*:responsible person)

  • IFO: damping work or others.
  • VAC: *Kimura
    • Pumping down will start ~10am today.

Laser hazard

  • [AM]
    • IR: PSL, Yend 1F
    • Green: off
  • [PM]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off
  • [night]
    • IR: Upstream SR2-3 line, Yend 1F
    • Green: off

Weekly

  • week of 4/9
    • 4/11 12:30 at fan hut: Meeting before pump down 2.
    • Closing EXC.
    • Some controls for Michelson.
    • 4/13 morning: Pump down starts.
  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues