Line 9: Line 9:
  * There are 3 ways;   * There are 3 ways to the operation in the newt week;
Line 25: Line 25:
 * BS: Eleonora, Izumi  * BS: *Eleonora, Izumi
Line 35: Line 35:
 * IFO: Enomoto, Nakano  * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora

2018/4/18(Wed.)

* Remote participants by eZuce: None

Report of work (*:responsible person)

  • VAC: *Kimura
    • One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today.
    • There are 3 ways to the operation in the newt week;
      • Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay.

      • Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days.

      • Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX.

  • ETMX: *Hasegawa
    • TF for MM coupling of photo sensor was found.
    • RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something.
  • ETMY: *Nakano, Shishido
    • Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad.
  • IFO: *Enomoto, Izumi
    • Trial lock of Michelson did not succeed because of too much motion of ETMY.
  • BS: *Eleonora, Izumi
    • We are optimizing diagonalization of L2P filter. Needs more time.
  • DGS: *Yamamoto
    • Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again.

Work plan (*:responsible person)

  • IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora
    • Damping, BS L2P, restoring alignment.
  • VAC: *Kimura
    • Identifies the location of leak.

Laser hazard

  • [AM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [PM]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F
  • [night]
    • IR: Upstream SR2-3 line, Xend 1F, Yend 1F
    • Green: PR2, Xend 1F

Weekly

  • week of 4/16
    • Michelson control.
    • Leak check.
    • Opening the last gate valve.
  • week of 4/23
    • Operation

Issues

  • Large leak was found but it is not identified where it is.

KAGRA/Commissioning/DailyWork/2018-04-18 (last edited 2018-04-18 09:23:31 by OsamuMiyakawa)