=== 2018/4/18(Wed.) === * Remote participants by eZuce: None ==== Report of work (*:responsible person) ==== * VAC: *Kimura * One of the small leak was found where it was, but another large leak seems to exist. Leak hunting will last today. * There are 3 ways to the operation in the newt week; * Leak location will be found and fixed without vent. -> ETMX gate valve will open, no delay. * Leak location will be found and not fixed without vent. -> Vent on Wednesday and Thursday, fix leak on Friday, pump down on Friday. -> ETMX gate valve will open, delay for several days. * Leak location will not be found and not fixed. -> ETMX gate valve will not open, no delay, but it will be difficult to find beam at ETMX. * ETMX: *Hasegawa * TF for MM coupling of photo sensor was found. * RMS motion seems to be OK if the mirror is not kicked. Even if the mirror is kicked, damping speed is ~10min or something. * ETMY: *Nakano, Shishido * Yaw dampins seems to be OK. Coupling between pitch and yaw exists. After ~10min or so, oscillation starts up to 10urad. * IFO: *Enomoto, Izumi * Trial lock of Michelson did not succeed because of too much motion of ETMY. * BS: *Eleonora, Izumi * We are optimizing diagonalization of L2P filter. Needs more time. * DGS: *Yamamoto * Interface card for PCIe on k1ioo was exchanged and connection between RTPC and IO chassis was established again. ==== Work plan (*:responsible person) ==== * IFO, ETMs, BS: Enomoto, Nakano, Izumi, Hasegawa, Shishido, Eleonora * Damping, BS L2P, restoring alignment. * VAC: *Kimura * Identifies the location of leak. ==== Laser hazard ==== * [AM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [PM] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F * [night] * IR: Upstream SR2-3 line, Xend 1F, Yend 1F * Green: PR2, Xend 1F ==== Weekly ==== * week of 4/16 * Michelson control. * Leak check. * Opening the last gate valve. * week of 4/23 * Operation ==== Issues ==== * Large leak was found but it is not identified where it is.