Differences between revisions 1 and 2
Revision 1 as of 2018-08-21 13:07:42
Size: 641
Comment:
Revision 2 as of 2018-08-21 13:08:00
Size: 643
Comment:
Deletions are marked like this. Additions are marked like this.
Line 8: Line 8:
=== Attendance === ==== Attendance ====

2018/8/21(Tue.)

  • PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
  • Actual night work will start 9/3 (9/1, 9/2 are weekends).
  • We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
  • One Car (Serena) will be assigned to commissioning work.

Attendance

  • Control room: Yamamoto, Yokozawa
  • Fan hut: Tomaru, Aso, Saito, Enomoto, Akutsu

Transition from morning work (*:responsible person)

Report of work (*:responsible person)

Work plan (*:responsible person)

KAGRA/Commissioning/DailyWork/2018-08-21 (last edited 2018-08-21 13:08:14 by OsamuMiyakawa)