Line 11: Line 11:
  ----

2018/8/21(Tue.)

  • PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
  • Actual night work will start 9/3 (9/1, 9/2 are weekends).
  • We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
  • One Car (Serena) will be assigned to commissioning work.

Attendance

  • Control room: Yamamoto, Yokozawa
  • Fan hut: Tomaru, Aso, Saito, Enomoto, Akutsu


Transition from morning work (*:responsible person)

Report of work (*:responsible person)

Work plan (*:responsible person)