=== 2018/8/22(Wed.) === * PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer. * Actual night work will start 9/3 (9/1, 9/2 are weekends). * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi. * One Car (Serena) will be assigned to commissioning work. ==== Attendance ==== * Control room: Miyakawa, Akutsu, Yamamoto, Yokozawa, Enomoto * Fan hut: * educe: Kokeyama ---- ==== Transition from morning work (*:responsible person) ==== * ==== Report of work (*:responsible person) ==== * Illuminator was not finished, it will be installed Tomorrow. '(Yokozawa) * ALS rack is being prepared. (Enomoto) * NAB white tape was removed. * IP of ITMX was released and tuned. ==== Work plan (*:responsible person) ==== * MC will be restored today.