=== 2018/8/27(Mon.) === * PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer. * Actual night work will start 9/3 (9/1, 9/2 are weekends). * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi. * One Car (Serena) will be assigned to commissioning work. ==== Attendance ==== * Control room: Enomoto, Miyakawa, Ushiba * Fan hut: * educe: ---- ==== Transition from morning work (*:responsible person) ==== * ==== Report of work (*:responsible person) ==== * Alignment procedure was updated. * ==== Work plan (*:responsible person) ==== * Watchdog of 4 coil driver for CRY should be removed.