2018/8/29(Wed.)

  • PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer.
    • Out put of PSL will be few Watts.
    • Safety for the high power laser should be announced.
  • Actual night work will start 9/3 (9/1, 9/2 are weekends).
  • We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi.
    • Furuta-san will attend this meeting every day to tell the laser hazard for Engineers.
  • One Car (Serena) will be assigned to commissioning work.

Attendance

  • Control room: Miyakawa, Kokeyama, Miyamoto, Kenta Tanaka
  • Fan hut: Nakano, Yamamoto
  • educe:

Laser hazard

Before 3PM

After 3PM

Center

upstream IMM

IR

IR

PSL

IR&Green

IR&Green

X end 1F

IR

IR

Y end 1F

N/A

N/A


Transition from morning work (*:responsible person)

Report of work (*:responsible person)

Work plan (*:responsible person)