=== 2018/8/30(Thur.) === * PSL for high-power laser will finish by 8/31 and they provides the high power laser to the interferometer. * Out put of PSL will be few Watts. * Safety for the high power laser should be announced. * Actual night work will start 9/3 (9/1, 9/2 are weekends). * We will have a daily meeting on 9/3 that is the first day of night work managed by Izumi. * Furuta-san will attend this meeting every day to tell the laser hazard for Engineers. * One Car (Serena) will be assigned to commissioning work. ==== Attendance ==== * Control room: Yamamoto * Fan hut: Miyakaw, Yokozawa, Takahashi, Kimura, Akutsu, Enomoto, Kozu * educe: ==== Laser hazard ==== |||| ||Before 3PM ||After 3PM || |||| || |||| ||Center||upstream IMM||IR ||IR || || ||PSL ||IR & Green||IR & Green|| ||||X end 1F ||IR ||IR || ||||Y end 1F ||N/A ||N/A || ---- ==== Transition from morning work (*:responsible person) ==== ==== Report of work (*:responsible person) ==== * Alignment preparation started. * Duct between IMM and IFI was moved and COACH filter was set there. * Test of PDA100 for ETMX was done. ==== Work plan (*:responsible person) ==== * Air will be introduced to PR2 and PR3 chamber to keep clean by having higher pressure. * O-rings should be kept clean during opening doors. * We do not have any more spare of O-ring. * O-ring for PR3 should be checked.