Differences between revisions 1 and 2
Revision 1 as of 2018-09-05 12:56:13
Size: 800
Comment:
Revision 2 as of 2018-09-05 13:14:21
Size: 1215
Comment:
Deletions are marked like this. Additions are marked like this.
Line 2: Line 2:
 * How about the day and night work on Saturday or Sunday.
Line 6: Line 6:
 * Fan hut:
 * educe:
 * Fan hut: Miyakawa, Takahashi(ICRR), Enomoto, Izumi, Yokozawa, Kimura, Kokeyama
 * educe: Takahashi
Line 25: Line 25:
 *
 * Leak test will be extended to Friday or Saturday.
 * Due on mirror will last for a while. It is not sure when we can inject Nitrogen.
Line 28: Line 30:
 *  * Green laser is injected into POP table. The power is 10mW and table is covered for the safety.
Line 31: Line 33:
 * Cable clean up on ETMY will be on Thursday.
Line 32: Line 35:

2018/9/5(Wed.)

  • How about the day and night work on Saturday or Sunday.

Attendance

  • Control room:
  • Fan hut: Miyakawa, Takahashi(ICRR), Enomoto, Izumi, Yokozawa, Kimura, Kokeyama
  • educe: Takahashi

Laser hazard

Before 3PM

After 3PM

Center

PSL

IR & Green

IR & Green

Center

upstream IMM

IR

IR

Center

around PR2

IR & Green

IR & Green

Center

behinde SR2-3 line

N/A

IR

X end 1F

IR

IR

Y end 1F

N/A

N/A

Night workers

  • Izumi, Enomoto, Eleonora,

Transition from morning work (*:responsible person)

  • Leak test will be extended to Friday or Saturday.
  • Due on mirror will last for a while. It is not sure when we can inject Nitrogen.

Report of work (*:responsible person)

  • Green laser is injected into POP table. The power is 10mW and table is covered for the safety.

Work plan (*:responsible person)

  • Cable clean up on ETMY will be on Thursday.

KAGRA/Commissioning/DailyWork/2018-09-05 (last edited 2018-09-05 13:14:21 by OsamuMiyakawa)