=== 2018/9/6(Thur.) ===
 * How about the day and night work on Saturday or Sunday.

==== Attendance ====
 * Control room: Izumi, Akutsu, Anna
 * Fan hut: Miyakawa, Takahashi(ICRR), Enomoto, Yokozawa, Kimura, Ueda
 * eZuce:

==== Laser hazard ====

||||                        ||Before 3PM||After 3PM||
||||                        ||          ||||
||Center||PSL               ||IR & Green||IR & Green||
||Center||upstream IMM      ||IR        ||IR        ||
||Center||around PR2        ||IR & Green||IR & Green||
||Center||behinde SR2-3 line||N/A       ||IR & Green||
||||X end 1F                ||N/A       ||IR & Green||
||||Y end 1F                ||N/A       ||N/A       ||

==== Night workers ====

 * Izumi, Enomoto, Eleonora

==== Transition from morning work (*:responsible person) ====
 * ETMY rack was stopped.

==== Report of work (*:responsible person) ====

 * Cleaning cable of ETMY rack was done.
 * DAC made 1Hz sound at the PSL.
 * IMC did not work yesterday. Changing some gain and threshold made lock.
  * This morning FSS did not work again.

==== Work plan (*:responsible person) ====
 * We will introduce beam up to BS.