2018/11/9(Fri.)
Attendance
- Control room: Yamamoto, Oshino, Lucia, Fukunaga, Nakano, Enomoto, Nakano
- Fan hut:
- Zoom: Enomoto
Laser hazard
|
Before 3PM |
After 3PM |
|
|
|
|
|
Center |
PSL |
IR & Green |
IR & Green |
Center |
around PR2 |
IR & Green |
IR & Green |
Center |
behinde SR2&Yfront |
IR |
IR |
X end 1F |
IR & Green |
IR & Green |
|
Y end 1F |
N/A |
N/A |
Night workers in the mine
- MIF: Enomoto, Michimura, Nakano
Weekend
- Saturday: Mio, Nakano, K.Yamamoto, Enomoto
Transition from morning work (*:responsible person)
- FSS lock loss was fixed.
Report of work (*:responsible person)
- 2hours lock of green has been established.
Work plan (*:responsible person)
- Needs some estimation for servo of Green.