=== 2019/1/15(Tue.) === === Weekend === * Some work for Y arm alignment. ==== Transition from morning work (*:responsible person) ==== ==== Report of work (*:responsible person) ==== * MC was aligned and chamber doors was closed. MC is ready for IFO alignnment. * CAL: Noise hunting. Cutting 5pin of D-SUB cable made 30dB improvement. * PEM: Ondotori setting was finished. We will be added 10 more. * AOS: Done finalization of Y front. Will work on ETMX this week. Needs heavy work inside the ETMX chamber. ==== Work plan (*:responsible person) ==== * Type B: We will do hight adjustments and some tuning for BS or other VIS. * Type A: Needs work at ITMY today. * DGS: We will separate the current rack at ETMX to the second one. It takes whole of this week. * DGS: RFM ID will be changed at ETMX and ETMY.