=== 2019/1/18(Fri.) === === Weekend === * Nakano, Enomoto, Yokozawa, Yokogawa, Tomaru, Ushiba Guiguo : Some work for Y arm alignment. ==== Transition from morning work (*:responsible person) ==== * If you open chamber or flange, you must put a label on the door/flange for "when/who" oped/closed door, and leave "current status". * COMM: SR alignment will be proceeded in the middle or late of next week ==== Report of work (*:responsible person) ==== * IMC: ASC loop was closed. Lock lasted all the night. * COMM: Beam is hitting on the center of PR2. * PR2: We saw the big pitch difference on Oplev as before. * ITMY : IP matrix tuning was done. * Needs more time for damping. ITMY will be ready next week for SR alignment. * MIR: Yokozawa, Kimura, Tomaru checked the surface of ETMY mirror. It was found that the surface was very dirty by eye and Tcam. * It is not sure for the cleaning. * WAB ETMX: Completed and moved in the safe mode. Needs a small remaining work for ITMY. ==== Work plan (*:responsible person) ==== * PR2 and PR3: we will open doors. * Type B: needs tuning for BS frequency. GEO phone is something wrong. * DGS: X end rack maintenance will finish this Friday or beginning of next week.