==== Report of work (*:responsible person) ====
 *
 * BS: Two cables were not connected well, so actuation was not correct when measuring TF day before yesterday.
  * TF was measured yesterday but still TF showed something different from the last correct measurement.
  * FR moved 800um.
  * Anyway alignment can be proceeded probably this afternoon.

 * CRY: we found disconnected cables at ITMX.

 * OMC: OMMT was aligned, and it was found that OSEM was touched somewhere.
 * PEM: Ondotori is still not working because of software issue.


==== Work plan (*:responsible person) ====

 * COMM: we will check PR3 first, then SR3.
  * Access to PR3 is quite difficult, gate valve needs to be removed or optical table needs to be fix.
  * we will decide whether we need clean the mirror surface or not.
  * Once mirror inspection and cleaning (if necessary), then will start alignment for REFL using reflected beam from ITMX.
 * COMM: PDA will be placed EYA.

 * SR3, SR2: height is OK. FR will be tuned.
  * SR3 surface will be inspected.

2019/1/23(Wed.)

Weekend

Transition from morning work (*:responsible person)

  • Schedule
    • Current status as of 1/22: IR and Green reached X end PD.
    • 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.
    • 1/22 or 23 Surface inspection for SR mirrors.
    • 1/23-25 Cleaning HR of SR2.
    • 1/23 BS will be aligned to Y-end PD by IR.
    • 1/24-25 ITMX will be aligned to REFL by IR.
      • 1/24-25 ITMY will be aligned to REFL by IR.
    • 1/26 Beam position of IR at SR3 will be confirmed how far from the center.
    • 1/28-29 SR3 will be aligned to SR2 center by IR.
    • 1/30 Green beam will be injected from SR2 AR surface to Y end PD.
    • 1/31-2/1 Removing bellows at PR and SR area.
    • 1/31-2/1 Cleaning HR of PR3 and AR of SR2
    • 2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR

    • 2/4-8 Alignment of ETMY -> POS by Green

    • 2/12-15 Closing door for central area, pumping down
      • needs drift monitor for VIS

Report of work (*:responsible person)

  • BS: Two cables were not connected well, so actuation was not correct when measuring TF day before yesterday.
    • TF was measured yesterday but still TF showed something different from the last correct measurement.
    • FR moved 800um.
    • Anyway alignment can be proceeded probably this afternoon.
  • CRY: we found disconnected cables at ITMX.
  • OMC: OMMT was aligned, and it was found that OSEM was touched somewhere.
  • PEM: Ondotori is still not working because of software issue.

Work plan (*:responsible person)

  • COMM: we will check PR3 first, then SR3.
    • Access to PR3 is quite difficult, gate valve needs to be removed or optical table needs to be fix.
    • we will decide whether we need clean the mirror surface or not.
    • Once mirror inspection and cleaning (if necessary), then will start alignment for REFL using reflected beam from ITMX.
  • COMM: PDA will be placed EYA.
  • SR3, SR2: height is OK. FR will be tuned.
    • SR3 surface will be inspected.