2019/1/23(Wed.)
Weekend
Transition from morning work (*:responsible person)
- Schedule
- Current status as of 1/22: IR and Green reached X end PD.
- 1/22 Surface inspection for PR mirrors. Cleaning will be done after 1/31.
- 1/22 or 23 Surface inspection for SR mirrors.
- 1/23-25 Cleaning HR of SR2.
- 1/23 BS will be aligned to Y-end PD by IR.
- 1/24-25 ITMX will be aligned to REFL by IR.
- 1/24-25 ITMY will be aligned to REFL by IR.
- 1/26 Beam position of IR at SR3 will be confirmed how far from the center.
- 1/28-29 SR3 will be aligned to SR2 center by IR.
- 1/30 Green beam will be injected from SR2 AR surface to Y end PD.
- 1/31-2/1 Removing bellows at PR and SR area.
- 1/31-2/1 Cleaning HR of PR3 and AR of SR2
2/4-8 Alignment of SR2 -> SRM by IR, SRM -> OMMT by IR -> OMMT -> OSTM by IR, OSTM -> OMC by IR
2/4-8 Alignment of ETMY -> POS by Green
- 2/12-15 Closing door for central area, pumping down
- needs drift monitor for VIS